Solar PV Panels & Battery Storage Facility (49.9 MW, REPD 11636)
Solar PV Panels & Battery Storage Facility is a 49.9 MW battery storage project in Stroud, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 15 December 2022; the record was last updated on 15 July 2022.
49.9 MWbattery storage
application withdrawnstatus in REPD
15 July 2022record last updated
Stroudcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 30 June 2022 | Application submitted |
| 15 December 2022 | Application withdrawn |
Project details
- Technology
- battery storage (co-located with re)
- Capacity
- 49.9 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 15 July 2022
- Operator or applicant
- Kronos Solar
- Planning authority
- Stroud
- Planning application reference
- S.22/1371/FUL
- Address (REPD)
- Milton End Farm Arlingham
- Council area (by location)
- Stroud
- Name in REPD
- Arlingham Solar Farm - Solar PV Panels & Battery Storage Facility
- REPD reference
- 11636
Recorded together with Leaps Rigg Solar Farm (49.9 MW solar farm, approved, not built).
Who decides
| Applications | Stroud | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 34 | 10,236 |
| Refused | 8 (24%) | 19% |
| Solar refused | 4 of 25 | 12% |
| Onshore wind refused | 3 of 4 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 17.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Solar PV Panels & Battery Storage Facility | solar farm | 49.9 | application withdrawn | <0.1 |
| Gravel Farm, Cleeve Solar Farm | solar farm | 32 | application withdrawn | 2.3 |
| Awre Penisular Farmer's Community Solar Scheme | solar farm | 49.9 | refused | 2.3 |
| Northington Lane | battery storage | 35 | approved, not built | 2.5 |
| Stantway Solar Farm | solar farm | 5 | operational | 3.1 |
| Cowles Farm | solar farm | 5 | refused on appeal | 3.8 |
| Solar Panels at Ne/O Poulton Court Farm | solar farm | 40 | application submitted | 4.5 |
| Epney, Framilode Solar Farm & Battery Storage | solar farm | 49.5 | refused | 4.7 |
| High Green Longney Estate Solar Farm | solar farm | 25 | permission expired | 6.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.795, -2.4141).