Energy Projects Near You

Solar, wind and battery projects near Drybrook (GL17)

17 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL17 (Forest of Dean): 2 are waiting for a planning decision, 6 approved but not yet running, 3 operational. The largest live scheme is Locquiers Farm, Plump Hill Solar Farm (15.7 MW solar farm, approved on 15 December 2021, not yet built; REPD status may be out of date), 0.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17projects within 10 km
2awaiting a decision
6approved, not running
3operational

Projects within 10 km of GL17

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Locquiers Farm, Plump Hill Solar Farmsolar farmsolar farm15.7approved, not built may be out of dateupdated Jan 2022May 2021granted Dec 2021Jan 2022Forest of Dean0.7
Vantage Pointrooftop solarrooftop solar1.4operationalupdated Mar 2016May 2011granted Jun 2011Mar 2016Forest of Dean2.3
Vantage Point Business Parksolar farmsolar farm3.6refusedupdated Mar 2015Jan 2015refused Mar 2015Mar 2015Forest of Dean2.7
Leeways Packaging Services, Laymore Roadrooftop solarrooftop solar1approved, not builtupdated Dec 2022Oct 2022granted Nov 2022Dec 2022Forest of Dean3.2
Cowles Farmsolar farmsolar farm5refused on appealupdated Feb 2017Jul 2015refused Oct 2015Feb 2017Forest of Dean6.0
Stantway Solar Farmsolar farmsolar farm5operationalupdated Aug 2014Jan 2011granted Apr 2011Aug 2014Forest of Dean8.6
Foxs Lanebattery storagebattery storage5application withdrawnupdated Nov 2018May 2017—Nov 2018Forest of Dean8.7
A J Lowther and Son Premisesolar farmsolar farm1under constructionupdated Jan 2022Aug 2019granted Oct 2020Jan 2022Herefordshire9.1
Gravel Farm, Cleeve Solar Farmsolar farmsolar farm32application withdrawnupdated Apr 2024Jan 2023—Apr 2024Forest of Dean9.1
Solar PV Panels & Battery Storage Facilitysolar farmsolar farm49.9application withdrawnupdated Mar 2021Jun 2022—Mar 2021Stroud9.5
Solar PV Panels & Battery Storage Facilitybattery storagebattery storage49.9application withdrawnupdated Jul 2022Jun 2022—Jul 2022Stroud9.5
Severn & Wye, Claxhill Solar Panels & Battery Energy Storage Systemsolar farmsolar farm1application submittedupdated Mar 2025Feb 2025—Mar 2025Forest of Dean9.5
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Chessgrove Farm, Chessgrove Lane Solar Arraysrooftop solarrooftop solar—approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Forest of Dean3.7
Walford Saw Millsrooftop solarrooftop solar0.1approved, not builtupdated Sep 2021Mar 2021granted May 2021Sep 2021Herefordshire6.7
Woodgate Sawmills, Buckstone Closerooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022Forest of Dean8.3
Severn & Wye, Claxhill Solar Panels & Battery Energy Storage Systembattery storagebattery storage—application submittedupdated Mar 2025Feb 2025—Mar 2025Forest of Dean9.5
Leewayssolar farmsolar farm0.5operationalupdated Nov 2019Oct 2018granted Jan 2019Nov 2019Forest of Dean9.9

Distance from the average position of the GL17 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm9122217.7
Rooftop solar504101.5
Battery storage310000

MW in pipeline: pending, approved and under-construction capacity.

How Forest of Dean decides solar, wind and battery applications

ApplicationsForest of DeanUK
Decided applications (solar, wind, battery)2810,236
Refused8 (29%)19%
Solar refused7 of 2612%
Battery storage refused1 of 216%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

All projects in Forest of Dean

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GL17, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.