Energy Projects Near You

Cowles Farm (5 MW solar farm)

Cowles Farm is a 5 MW solar farm project in Forest of Dean, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 7 February 2017; the record was last updated on 28 February 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refused on appealstatus in REPD
28 February 2017record last updated
Forest of Deancouncil area

Planning timeline

DateStage
1 July 2015Application submitted
15 October 2015Refused by the planning authority
29 April 2016Appeal lodged
7 February 2017Appeal refused

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused on appeal
Record last updated
28 February 2017
Operator or applicant
Wessex Solar Energy
Planning authority
Forest of Dean
Planning application reference
P0856/15/FUL
Appeal reference
APP/P1615/W/16/3148113
Site area
8.3 ha
Address (REPD)
Cowles Farm, Elton Road, Elton, Newnham, Gloucestershire
Council area (by location)
Forest of Dean
Time to decision
15 weeks
REPD reference
5446

Who decides

ApplicationsForest of DeanUK
Decided applications (solar, wind, battery)2810,236
Refused8 (29%)19%
Solar refused7 of 2612%
Battery storage refused1 of 216%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stantway Solar Farmsolar farm5operational2.7
Gravel Farm, Cleeve Solar Farmsolar farm32application withdrawn3.2
Solar PV Panels & Battery Storage Facilitysolar farm49.9application withdrawn3.8
Solar PV Panels & Battery Storage Facilitybattery storage49.9application withdrawn3.8
Locquiers Farm, Plump Hill Solar Farmsolar farm15.7approved, not built5.3
Northington Lanebattery storage35approved, not built5.5
Awre Penisular Farmer's Community Solar Schemesolar farm49.9refused5.8
Epney, Framilode Solar Farm & Battery Storagesolar farm49.5refused7.1
Solar Panels at Ne/O Poulton Court Farmsolar farm40application submitted7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8261, -2.4384).