Stantway Solar Farm (5 MW)

Stantway Solar Farm is a 5 MW solar farm project in Forest of Dean, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 March 2014; the record was last updated on 26 August 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
26 August 2014record last updated
Forest of Deancouncil area

Planning timeline

DateStage
12 January 2011Application submitted
13 April 2011Planning permission granted
29 March 2014Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
26 August 2014
Operator or applicant
Private Developer
Planning authority
Forest of Dean
Planning application reference
P0031/11/FUL
Site area
13.9 ha
Address (REPD)
Rodley Court Farm, Westbury On Severn Gloucestershire GL14 1QG
Council area (by location)
Forest of Dean
Time to decision
13 weeks
REPD reference
2063

Who decides

ApplicationsForest of DeanUK
Decided applications (solar, wind, battery)2810,236
Refused8 (29%)19%
Solar refused7 of 2612%
Battery storage refused1 of 216%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gravel Farm, Cleeve Solar Farmsolar farm32application withdrawn0.9
Cowles Farmsolar farm5refused on appeal2.7
Solar PV Panels & Battery Storage Facilitysolar farm49.9application withdrawn3.1
Solar PV Panels & Battery Storage Facilitybattery storage49.9application withdrawn3.1
Epney, Framilode Solar Farm & Battery Storagesolar farm49.5refused4.5
High Green Longney Estate Solar Farmsolar farm25permission expired5.2
High Green Longney Estate Solar Farmsolar farm20permission expired5.2
Awre Penisular Farmer's Community Solar Schemesolar farm49.9refused5.4
Northington Lanebattery storage35approved, not built5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8212, -2.3998).