Epney, Framilode Solar Farm & Battery Storage (49.5 MW)

Epney, Framilode Solar Farm & Battery Storage is a 49.5 MW solar farm project in Stroud, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 4 December 2025; the record was last updated on 9 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.5 MWsolar farm
refusedstatus in REPD
9 December 2025record last updated
Stroudcouncil area

Planning timeline

DateStage
16 June 2025Application submitted
4 December 2025Refused by the planning authority

Project details

Technology
solar farm
Capacity
49.5 MW
Status (REPD)
refused
Record last updated
9 December 2025
Operator or applicant
PACE Tribute Energy Limited
Planning authority
Stroud
Planning application reference
S.25/1011/FUL
Site area
48.6 ha
Address (REPD)
Epney Framilode
Council area (by location)
Stroud
Time to decision
24 weeks
Name in REPD
Epney, Framilode - Solar Farm & Battery Storage
REPD reference
17804

Who decides

ApplicationsStroudUK
Decided applications (solar, wind, battery)3410,236
Refused8 (24%)19%
Solar refused4 of 2512%
Onshore wind refused3 of 445%
Battery storage refused1 of 516%
Median time from submission to decision17.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
High Green Longney Estate Solar Farmsolar farm25permission expired1.7
High Green Longney Estate Solar Farmsolar farm20permission expired1.7
Moreton Lane Solar Farm & Battery Storagesolar farm49.9approved, not built2.3
Gravel Farm, Cleeve Solar Farmsolar farm32application withdrawn3.9
Stantway Solar Farmsolar farm5operational4.5
Solar PV Panels & Battery Storage Facilitysolar farm49.9application withdrawn4.7
Solar PV Panels & Battery Storage Facilitybattery storage49.9application withdrawn4.7
Awre Penisular Farmer's Community Solar Schemesolar farm49.9refused5.8
Northington Lanebattery storage35approved, not built6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7978, -2.3461).