Energy Projects Near You

Northington Lane (35 MW battery storage)

Northington Lane is a 35 MW battery storage project in Forest of Dean, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 9 May 2023, not yet built; the record was last updated on 23 November 2021. REPD also records that the planning permission expired on 9 May 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWbattery storage
approved, not builtmay be out of datestatus in REPD
23 November 2021record last updated
Forest of Deancouncil area

REPD also records that the planning permission expired on 9 May 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
11 November 2021Application submitted
12 May 2022Refused by the planning authority
16 September 2022Appeal lodged
9 May 2023Planning permission granted
9 May 2023Appeal allowed
9 May 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
35 MW
Status (REPD)
approved, not built
Record last updated
23 November 2021
Operator or applicant
Green Frog Ventures Limited
Planning authority
Forest of Dean
Planning application reference
P1817/21/FUL
Appeal reference
AP0026/22/REF
Address (REPD)
Northington Lane, Awre
Council area (by location)
Forest of Dean
Time to decision
78 weeks
Name in REPD
Northington Lane - Battery Storage Facility
REPD reference
9992

Who decides

ApplicationsForest of DeanUK
Decided applications (solar, wind, battery)2810,236
Refused8 (29%)19%
Solar refused7 of 2612%
Battery storage refused1 of 216%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Awre Penisular Farmer's Community Solar Schemesolar farm49.9refused0.9
Solar Panels at Ne/O Poulton Court Farmsolar farm40application submitted2.0
Solar PV Panels & Battery Storage Facilitysolar farm49.9application withdrawn2.5
Solar PV Panels & Battery Storage Facilitybattery storage49.9application withdrawn2.5
Gravel Farm, Cleeve Solar Farmsolar farm32application withdrawn4.8
Cowles Farmsolar farm5refused on appeal5.5
Stantway Solar Farmsolar farm5operational5.5
Kingston Road, Slimbridgebattery storage36approved, not built5.6
Nibley Mill Farmsolar farm15.9refused6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7764, -2.4349).