Energy Projects Near You

Solar, wind and battery projects near Cinderford (GL14)

23 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL14 (Forest of Dean): 3 are waiting for a planning decision, 6 approved but not yet running, 5 operational. The largest live scheme is Solar Panels at Ne/O Poulton Court Farm (40 MW solar farm, application submitted on 6 May 2025, no decision recorded), 6.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23projects within 10 km
3awaiting a decision
6approved, not running
5operational

Projects within 10 km of GL14

Projects of 1 MW and more (17)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Leeways Packaging Services, Laymore Roadrooftop solarrooftop solar1approved, not builtupdated Dec 2022Oct 2022granted Nov 2022Dec 2022Forest of Dean2.3
Cowles Farmsolar farmsolar farm5refused on appealupdated Feb 2017Jul 2015refused Oct 2015Feb 2017Forest of Dean3.1
Locquiers Farm, Plump Hill Solar Farmsolar farmsolar farm15.7approved, not built may be out of dateupdated Jan 2022May 2021granted Dec 2021Jan 2022Forest of Dean4.1
Solar PV Panels & Battery Storage Facilitysolar farmsolar farm49.9application withdrawnupdated Mar 2021Jun 2022—Mar 2021Stroud5.3
Solar PV Panels & Battery Storage Facilitybattery storagebattery storage49.9application withdrawnupdated Jul 2022Jun 2022—Jul 2022Stroud5.3
Vantage Pointrooftop solarrooftop solar1.4operationalupdated Mar 2016May 2011granted Jun 2011Mar 2016Forest of Dean5.5
Northington Lanebattery storagebattery storage35approved, not built may be out of dateupdated Nov 2021Nov 2021granted May 2023Nov 2021Forest of Dean5.6
Stantway Solar Farmsolar farmsolar farm5operationalupdated Aug 2014Jan 2011granted Apr 2011Aug 2014Forest of Dean5.6
Gravel Farm, Cleeve Solar Farmsolar farmsolar farm32application withdrawnupdated Apr 2024Jan 2023—Apr 2024Forest of Dean5.8
Vantage Point Business Parksolar farmsolar farm3.6refusedupdated Mar 2015Jan 2015refused Mar 2015Mar 2015Forest of Dean5.9
Awre Penisular Farmer's Community Solar Schemesolar farmsolar farm49.9refusedupdated Dec 2017Jun 2015refused Jan 2016Dec 2017Forest of Dean6.3
Solar Panels at Ne/O Poulton Court Farmsolar farmsolar farm40application submittedupdated Jun 2025May 2025—Jun 2025Forest of Dean6.7
Severn & Wye, Claxhill Solar Panels & Battery Energy Storage Systemsolar farmsolar farm1application submittedupdated Mar 2025Feb 2025—Mar 2025Forest of Dean6.9
Foxs Lanebattery storagebattery storage5application withdrawnupdated Nov 2018May 2017—Nov 2018Forest of Dean8.0
Nibley Mill Farmsolar farmsolar farm15.9refusedupdated Sep 2014May 2014refused Sep 2014Sep 2014Forest of Dean8.6
Yorkley Solar Parksolar farmsolar farm5operationalupdated Jan 2016May 2015granted Jun 2015Jan 2016Forest of Dean8.8
Epney, Framilode Solar Farm & Battery Storagesolar farmsolar farm49.5refusedupdated Dec 2025Jun 2025refused Dec 2025Dec 2025Stroud9.6
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Chessgrove Farm, Chessgrove Lane Solar Arraysrooftop solarrooftop solar—approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Forest of Dean6.0
Severn & Wye, Claxhill Solar Panels & Battery Energy Storage Systembattery storagebattery storage—application submittedupdated Mar 2025Feb 2025—Mar 2025Forest of Dean6.9
Woodgate Sawmills, Buckstone Closerooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022Forest of Dean8.3
Shipton Mill Limited, Frampton On Severn Industrial Parkrooftop solarrooftop solar0.2approved, not builtupdated Oct 2024Aug 2024granted Sep 2024Oct 2024Stroud9.2
Jones Food Company Solar Farmrooftop solarrooftop solar0.7operationalupdated Feb 2024——Feb 2024Forest of Dean9.4
Leewayssolar farmsolar farm0.5operationalupdated Nov 2019Oct 2018granted Jan 2019Nov 2019Forest of Dean9.4

Distance from the average position of the GL14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm13213556.7
Rooftop solar604201.5
Battery storage4110035

MW in pipeline: pending, approved and under-construction capacity.

How Forest of Dean decides solar, wind and battery applications

ApplicationsForest of DeanUK
Decided applications (solar, wind, battery)2810,236
Refused8 (29%)19%
Solar refused7 of 2612%
Battery storage refused1 of 216%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

All projects in Forest of Dean

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GL14, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.