Energy Projects Near You

Locquiers Farm, Plump Hill Solar Farm (15.7 MW)

Locquiers Farm, Plump Hill Solar Farm is a 15.7 MW solar farm project in Forest of Dean, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 December 2021, not yet built; the record was last updated on 18 January 2022. REPD records the planning permission as expiring on 15 December 2024, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15.7 MWsolar farm
approved, not builtmay be out of datestatus in REPD
18 January 2022record last updated
Forest of Deancouncil area

REPD records the planning permission as expiring on 15 December 2024, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
24 May 2021Application submitted
15 December 2021Planning permission granted
15 December 2024Permission expired

Project details

Technology
solar farm
Capacity
15.7 MW
Status (REPD)
approved, not built
Record last updated
18 January 2022
Operator or applicant
Opdenergy UK 3 Limited
Planning authority
Forest of Dean
Planning application reference
P0980/21/FUL
Site area
18.5 ha
Address (REPD)
Locquiers Farm Plump Hill Mitcheldean
Council area (by location)
Forest of Dean
Time to decision
29 weeks
Contracts for Difference
AR5
Name in REPD
Locquiers Farm, Plump Hill - Solar Farm
REPD reference
9114

Who decides

ApplicationsForest of DeanUK
Decided applications (solar, wind, battery)2810,236
Refused8 (29%)19%
Solar refused7 of 2612%
Battery storage refused1 of 216%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cowles Farmsolar farm5refused on appeal5.3
Stantway Solar Farmsolar farm5operational7.9
Gravel Farm, Cleeve Solar Farmsolar farm32application withdrawn8.5
Foxs Lanebattery storage5application withdrawn8.7
Solar PV Panels & Battery Storage Facilitysolar farm49.9application withdrawn8.8
Solar PV Panels & Battery Storage Facilitybattery storage49.9application withdrawn8.8
Northington Lanebattery storage35approved, not built9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8515, -2.5042).