Energy Projects Near You

Solar, wind and battery projects near Ross-on-Wye (HR9)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of HR9 (Herefordshire): 5 approved but not yet running, 2 operational. The largest live scheme is Peterstow Gas Compressor Station, Hentland (49.9 MW battery storage, approved on 19 March 2025, not yet built), 5.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
5approved, not running
2operational

Projects within 10 km of HR9

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Peterstow Gas Compressor Station, Hentlandbattery storagebattery storage49.9approved, not builtupdated Jun 2026May 2023granted Mar 2025Jun 2026Herefordshire5.3
A J Lowther and Son Premisesolar farmsolar farm1under constructionupdated Jan 2022Aug 2019granted Oct 2020Jan 2022Herefordshire6.6
Vantage Pointrooftop solarrooftop solar1.4operationalupdated Mar 2016May 2011granted Jun 2011Mar 2016Forest of Dean8.0
Vantage Point Business Parksolar farmsolar farm3.6refusedupdated Mar 2015Jan 2015refused Mar 2015Mar 2015Forest of Dean8.0
Locquiers Farm, Plump Hill Solar Farmsolar farmsolar farm15.7approved, not built may be out of dateupdated Jan 2022May 2021granted Dec 2021Jan 2022Forest of Dean8.2
Witches Solar Farmsolar farmsolar farm5operationalupdated May 2014Nov 2010granted Feb 2011May 2014Herefordshire9.6
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Walford Saw Millsrooftop solarrooftop solar0.1approved, not builtupdated Sep 2021Mar 2021granted May 2021Sep 2021Herefordshire3.8
Chessgrove Farm, Chessgrove Lane Solar Arraysrooftop solarrooftop solar—approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Forest of Dean9.1

Distance from the average position of the HR9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm4021116.7
Rooftop solar302100.1
Battery storage1010049.9

MW in pipeline: pending, approved and under-construction capacity.

How Herefordshire decides solar, wind and battery applications

ApplicationsHerefordshireUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused6 of 2712%
Onshore wind refused0 of 145%
Battery storage refused0 of 716%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

All projects in Herefordshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near HR9, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.