Energy Projects Near You

Solar, wind and battery projects near Coleford (GL16)

12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL16 (Forest of Dean): 6 approved but not yet running, 4 operational. The largest live scheme is Locquiers Farm, Plump Hill Solar Farm (15.7 MW solar farm, approved on 15 December 2021, not yet built; REPD status may be out of date), 9.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12projects within 10 km
0awaiting a decision
6approved, not running
4operational

Projects within 10 km of GL16

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Foxs Lanebattery storagebattery storage5application withdrawnupdated Nov 2018May 2017—Nov 2018Forest of Dean1.4
Pingry Farm - Phase 1solar farmsolar farm3.4operationalupdated May 2015Mar 2013granted Apr 2013May 2015Forest of Dean1.7
Pingry Farm - Phase 2solar farmsolar farm3.4operationalupdated May 2015Mar 2013granted Apr 2013May 2015Forest of Dean1.7
Leeways Packaging Services, Laymore Roadrooftop solarrooftop solar1approved, not builtupdated Dec 2022Oct 2022granted Nov 2022Dec 2022Forest of Dean7.7
Yorkley Solar Parksolar farmsolar farm5operationalupdated Jan 2016May 2015granted Jun 2015Jan 2016Forest of Dean7.7
A J Lowther and Son Premisesolar farmsolar farm1under constructionupdated Jan 2022Aug 2019granted Oct 2020Jan 2022Herefordshire7.8
Nibley Mill Farmsolar farmsolar farm15.9refusedupdated Sep 2014May 2014refused Sep 2014Sep 2014Forest of Dean9.6
Locquiers Farm, Plump Hill Solar Farmsolar farmsolar farm15.7approved, not built may be out of dateupdated Jan 2022May 2021granted Dec 2021Jan 2022Forest of Dean9.7
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Woodgate Sawmills, Buckstone Closerooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022Forest of Dean1.3
Noble Green Energyrooftop solarrooftop solar0.9approved, not builtupdated Dec 2025Oct 2025granted Dec 2025Dec 2025Forest of Dean2.9
Jones Food Company Solar Farmrooftop solarrooftop solar0.7operationalupdated Feb 2024——Feb 2024Forest of Dean8.7
Walford Saw Millsrooftop solarrooftop solar0.1approved, not builtupdated Sep 2021Mar 2021granted May 2021Sep 2021Herefordshire8.9

Distance from the average position of the GL16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm6023116.7
Rooftop solar504102.4
Battery storage100000

MW in pipeline: pending, approved and under-construction capacity.

How Forest of Dean decides solar, wind and battery applications

ApplicationsForest of DeanUK
Decided applications (solar, wind, battery)2810,236
Refused8 (29%)19%
Solar refused7 of 2612%
Battery storage refused1 of 216%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

All projects in Forest of Dean

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GL16, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.