Energy Projects Near You

Solar, wind and battery projects near Monmouth (NP25)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NP25 (Monmouthshire): 3 approved but not yet running, 2 operational. The largest live scheme is A J Lowther and Son Premise (1 MW solar farm, under construction since 1 July 2021), 8.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
0awaiting a decision
3approved, not running
2operational

Projects within 10 km of NP25

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Pingry Farm - Phase 1solar farmsolar farm3.4operationalupdated May 2015Mar 2013granted Apr 2013May 2015Forest of Dean7.3
Pingry Farm - Phase 2solar farmsolar farm3.4operationalupdated May 2015Mar 2013granted Apr 2013May 2015Forest of Dean7.3
A J Lowther and Son Premisesolar farmsolar farm1under constructionupdated Jan 2022Aug 2019granted Oct 2020Jan 2022Herefordshire8.7
Foxs Lanebattery storagebattery storage5application withdrawnupdated Nov 2018May 2017—Nov 2018Forest of Dean9.1
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Noble Green Energyrooftop solarrooftop solar0.9approved, not builtupdated Dec 2025Oct 2025granted Dec 2025Dec 2025Forest of Dean8.3
Woodgate Sawmills, Buckstone Closerooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022Forest of Dean8.5

Distance from the average position of the NP25 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm301201
Rooftop solar202001.2
Battery storage100000

MW in pipeline: pending, approved and under-construction capacity.

How Monmouthshire decides solar, wind and battery applications

ApplicationsMonmouthshireUK
Decided applications (solar, wind, battery)1210,236
Refused2 (17%)19%
Solar refused2 of 1212%
Median time from submission to decision19.1 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Monmouthshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.