Energy Projects Near You

Renewable energy projects in Monmouthshire

15 solar, wind or battery projects of 150 kW or more are located in Monmouthshire (REPD, July 2026 extract): 0 pending, 5 approved but not running, 6 operational and 0 refused. The council refused 2 of 12 decided applications (17%; UK 19%), with a median 19 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15projects in the council area
0awaiting a decision
5approved, not running
17%of decisions refused

How Monmouthshire decides

ApplicationsMonmouthshireUK
Decided applications (solar, wind, battery)1210,236
Refused2 (17%)19%
Solar refused2 of 1212%
Median time from submission to decision19.1 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Projects in Monmouthshire

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Penpergwm Solar Farm (Great House Farm)solar farmsolar farm32under constructionupdated Apr 2026Jan 2022granted Jan 2023Apr 2026
Manor Farm (Monmouthshire)solar farmsolar farm10.5operationalupdated Sep 2016Jan 2013granted Oct 2014Sep 2016
Buckwell Farm Solar Parksolar farmsolar farm8.1abandonedupdated Dec 2019Oct 2013granted Aug 2014Dec 2019
Land at Lower House Farmsolar farmsolar farm8.1operationalupdated May 2016Aug 2012granted Dec 2012May 2016
Rhewl Farmsolar farmsolar farm6operationalupdated Jul 2016Aug 2014granted Jun 2015Jul 2016
Oak Grove Farmsolar farmsolar farm5.7operationalupdated Nov 2017Mar 2015—Nov 2017
Southbrook Solar Farmsolar farmsolar farm5operationalupdated Jun 2016Jul 2015granted Dec 2015Jun 2016
Land North West of Magor Service Stationsolar farmsolar farm5abandonedupdated Dec 2016May 2015granted Dec 2015Dec 2016
Llancayo Solar Farmsolar farmsolar farm3.9operationalupdated May 2012Apr 2011granted Jun 2011May 2012
Great House Farmwind farmwind farm3application withdrawnupdated Nov 2016Oct 2012—Nov 2016
Magor Breweryrooftop solarrooftop solar1.7abandonedupdated Jan 2020Sep 2015granted Oct 2015Jan 2020
Daisy Cottage, Ty-Canol Roadsolar farmsolar farm1approved, not builtupdated Nov 2022Aug 2022granted Oct 2022Nov 2022
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Newhouse Farm Industrial Estate, Unit 1rooftop solarrooftop solar0.3approved, not builtupdated Mar 2026Dec 2025granted Jan 2026Mar 2026
Morrisons, Abergavennyrooftop solarrooftop solar0.2approved, not builtupdated Jan 2022Nov 2021granted Mar 2022Jan 2022
Llanarth Court Hospital, Llanarth Roadrooftop solarrooftop solar—approved, not builtupdated Nov 2025Apr 2025granted Oct 2025Nov 2025

Postcode districts in Monmouthshire

DistrictProjects within 10 kmPendingApprovedOperational
NP75041
NP158023
NP169035
NP256032
NP26234111

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Monmouthshire by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.