Buckwell Farm Solar Park (8.1 MW)

Buckwell Farm Solar Park is an 8.1 MW solar farm project in Monmouthshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 4 December 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.1 MWsolar farm
abandonedstatus in REPD
4 December 2019record last updated
Monmouthshirecouncil area

Planning timeline

DateStage
31 October 2013Application submitted
6 August 2014Planning permission granted
6 August 2019Permission expired

Project details

Technology
solar farm
Capacity
8.1 MW
Status (REPD)
abandoned
Record last updated
4 December 2019
Operator or applicant
Private Developer
Planning authority
Monmouthshire
Planning application reference
DC/2013/00925
Address (REPD)
Buckwell Farm, Pen Y Cae Mawr Usk Monmouthshire
Council area (by location)
Monmouthshire
Time to decision
40 weeks
REPD reference
2106

Who decides

ApplicationsMonmouthshireUK
Decided applications (solar, wind, battery)1210,236
Refused2 (17%)19%
Solar refused2 of 1212%
Median time from submission to decision19.1 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Court Farmsolar farm8.5operational7.6
Rhewl Farmsolar farm6operational8.1
Land North West of Magor Service Stationsolar farm5abandoned8.5
Craig y Perthi Solar Farmsolar farm99.9refused9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6643, -2.8378).