Court Farm (8.5 MW solar farm)

Court Farm is an 8.5 MW solar farm project in Newport, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2017; the record was last updated on 4 October 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.5 MWsolar farm
operationalstatus in REPD
4 October 2017record last updated
Newportcouncil area

Planning timeline

DateStage
5 March 2015Application submitted
7 April 2015Refused by the planning authority
10 July 2015Appeal lodged
9 October 2015Planning permission granted
9 October 2015Appeal allowed
30 January 2017Construction started
30 March 2017Operational

Project details

Technology
solar farm
Capacity
8.5 MW
Status (REPD)
operational
Record last updated
4 October 2017
Operator or applicant
BE Renewables
Planning authority
Newport
Planning application reference
14/1275
Appeal reference
APP/G6935/A/15/3034087
Site area
13.0 ha
Address (REPD)
Land Forming Part Of Court Farm, Magor Road
Council area (by location)
Newport
Time to decision
31 weeks
REPD reference
5084

Earlier applications for this site

ApplicationMWSubmittedOutcome
Court Farm 13/12038.515 November 2013refused 1 October 2014

Who decides

ApplicationsNewportUK
Decided applications (solar, wind, battery)2210,236
Refused5 (23%)19%
Solar refused4 of 1312%
Onshore wind refused0 of 345%
Battery storage refused1 of 616%
Median time from submission to decision20.4 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Craig y Perthi Solar Farmsolar farm99.9refused1.9
Land North West of Magor Service Stationsolar farm5abandoned3.3
Abertillery Wind farmwind farm39.6application submitted4.5
Llanwern Solar Farm & Battery Storagesolar farm75operational4.7
Leeway House, Leeway Industrial Estatebattery storage20.6approved, not built5.8
Rush Wall Solar Parksolar farm75appeal lodged5.8
Solutia UK Ltdwind farm5operational7.0
Traston Roadbattery storage20operational7.1
Eastern Sitesolar farm5refused7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6011, -2.8787).