Eastern Site (5 MW solar farm)

Eastern Site is a 5 MW solar farm project in Newport, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 8 February 2016; the record was last updated on 4 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refusedstatus in REPD
4 March 2015record last updated
Newportcouncil area

Planning timeline

DateStage
22 July 2015Application submitted
8 February 2016Refused by the planning authority

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
4 March 2015
Operator or applicant
Lightsource Renewable Energy
Planning authority
Newport
Planning application reference
15/0903
Site area
11.2 ha
Address (REPD)
Land to NW of Lodge Farm, Lodge Hill, Caerleon
Council area (by location)
Newport
Time to decision
29 weeks
REPD reference
5546

Who decides

ApplicationsNewportUK
Decided applications (solar, wind, battery)2210,236
Refused5 (23%)19%
Solar refused4 of 1312%
Onshore wind refused0 of 345%
Battery storage refused1 of 616%
Median time from submission to decision20.4 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pentre Bach Solar Farmsolar farm20application submitted3.9
Leeway House, Leeway Industrial Estatebattery storage20.6approved, not built6.1
Mynydd Maen Wind Farmwind farm54.6application submitted6.2
Traston Roadbattery storage20operational6.2
Solutia UK Ltdwind farm5operational6.4
Cwrt Henllys Farmsolar farm5operational6.8
Land East of Panteg Waysolar farm5abandoned6.8
Court Farmsolar farm8.5operational7.5
Craig y Perthi Solar Farmsolar farm99.9refused7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6234, -2.9812).