Energy Projects Near You

Cwrt Henllys Farm (5 MW solar farm)

Cwrt Henllys Farm is a 5 MW solar farm project in Caerphilly, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 December 2016; the record was last updated on 30 June 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
30 June 2017record last updated
Caerphillycouncil area

Planning timeline

DateStage
22 July 2015Application submitted
16 June 2016Planning permission granted
29 October 2016Construction started
29 December 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
30 June 2017
Operator or applicant
Lightsource Renewable Energy
Planning authority
Torfaen
Planning application reference
15/P/00434
Site area
14.0 ha
Address (REPD)
Church Farm, Cwm Lane, Henllys, Cwmbran
Council area (by location)
Caerphilly
Time to decision
47 weeks
REPD reference
5524

Who decides

Torfaen has 6 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Pentre Bach Solar Farmsolar farm20application submitted2.9
Mynydd Maen Wind Farmwind farm54.6application submitted5.6
Penrhiwarwydd Farmsolar farm8.5operational5.6
Cwmcaesingrug Farmsolar farm10operational6.4
Eastern Sitesolar farm5refused6.8
Trecelyn Wind Farmwind farm20application submitted7.0
Upper Pant-Ysgawen Farm, Maes-Yr-Haf Lanebattery storage28application submitted7.6
Land East of Panteg Waysolar farm5abandoned8.0
Coal Pit Lanesolar5.3application withdrawn8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6214, -3.0794).