Energy Projects Near You

Penrhiwarwydd Farm (8.5 MW solar farm)

Penrhiwarwydd Farm is an 8.5 MW solar farm project in Caerphilly, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 March 2015; the record was last updated on 16 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.5 MWsolar farm
operationalstatus in REPD
16 April 2015record last updated
Caerphillycouncil area

Planning timeline

DateStage
29 July 2014Application submitted
7 November 2014Planning permission granted
1 January 2015Construction started
26 March 2015Operational

Project details

Technology
solar farm
Capacity
8.5 MW
Status (REPD)
operational
Record last updated
16 April 2015
Operator or applicant
MTS Hill Farm Solar Ltd
Planning authority
Caerphilly
Planning application reference
14/0512/FULL
Site area
18.9 ha
Address (REPD)
Penrhiwarwydd Farm Mynyddislwyn Mountain Road Mynyddislwyn Newport NP11 7BB
Council area (by location)
Caerphilly
Time to decision
14 weeks
REPD reference
2206

Who decides

ApplicationsCaerphillyUK
Decided applications (solar, wind, battery)1410,236
Refused4 (29%)19%
Solar refused0 of 712%
Onshore wind refused4 of 645%
Battery storage refused0 of 116%
Median time from submission to decision14.9 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cwmcaesingrug Farmsolar farm10operational0.8
Trecelyn Wind Farmwind farm20application submitted3.7
Upper Pant-Ysgawen Farm, Maes-Yr-Haf Lanebattery storage28application submitted4.4
Cwrt Henllys Farmsolar farm5operational5.6
Mynydd Llanhilleth Wind Farmwind farm34application submitted7.4
Cwm Ivor Penyrheol Solar Farmsolar farm20approved, not built7.4
Pentre Bach Solar Farmsolar farm20application submitted8.4
Mynydd Maen Wind Farmwind farm54.6application submitted8.9
Hendai Farmsolar farm13.4operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6327, -3.1582).