Energy Projects Near You

Renewable energy projects in Newport

37 solar, wind or battery projects of 150 kW or more are located in Newport (REPD, July 2026 extract): 6 pending, 10 approved but not running, 13 operational and 4 refused. The council refused 5 of 22 decided applications (23%; UK 19%), with a median 20 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

37projects in the council area
6awaiting a decision
10approved, not running
23%of decisions refused

How Newport decides

ApplicationsNewportUK
Decided applications (solar, wind, battery)2210,236
Refused5 (23%)19%
Solar refused4 of 1312%
Onshore wind refused0 of 345%
Battery storage refused1 of 616%
Median time from submission to decision20.4 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Projects in Newport

Projects of 1 MW and more (26)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Uskmouth Power Stationbattery storagebattery storage230under constructionupdated Feb 2025Aug 2022granted Dec 2022Feb 2025
Wentlooge Renewable Energy Hubsolar farmsolar farm125appeal lodged may be out of dateupdated Feb 2024Jun 2022—Feb 2024
Uskmouth Power Station, West Nash Roadbattery storagebattery storage120under constructionupdated Dec 2025Oct 2023granted Jan 2024Dec 2025
Craig y Perthi Solar Farmsolar farmsolar farm99.9refusedupdated Jan 2026Apr 2024refused Oct 2025Jan 2026
Llanwern Solar Farm & Battery Storagesolar farmsolar farm75operationalupdated Mar 2022Feb 2018granted Nov 2018Mar 2022
Rush Wall Solar Parksolar farmsolar farm75appeal lodged may be out of dateupdated Feb 2024Mar 2022—Feb 2024
Abertillery Wind farmwind farmwind farm39.6application submittedupdated Dec 2024Oct 2024—Dec 2024
Leeway House, Leeway Industrial Estatebattery storagebattery storage20.6approved, not builtupdated Aug 2025Feb 2025granted Jul 2025Aug 2025
Traston Roadbattery storagebattery storage20operationalupdated Feb 2026Aug 2016granted Nov 2016Feb 2026
Court Farmsolar farmsolar farm8.5operationalupdated Oct 2017Mar 2015granted Oct 2015Oct 2017
Coal Pit Lanesolarsolar5.3application withdrawnupdated Nov 2014Jun 2014—Nov 2014
Solutia UK Ltdwind farmwind farm5operationalupdated Oct 2013Nov 2008granted Jan 2009Oct 2013
Eastern Sitesolar farmsolar farm5refusedupdated Mar 2015Jul 2015refused Feb 2016Mar 2015
Newport (Began Road)solar farmsolar farm4.9operationalupdated Feb 2017Apr 2014granted Oct 2015Feb 2017
Land to North West of Lodge Farm (Park Farm)solar farmsolar farm4operationalupdated May 2017Jul 2015granted Feb 2016May 2017
Land To West Of Cefn Llogell Farmsolar farmsolar farm3.8refused on appealupdated Mar 2016May 2015refused Nov 2015Mar 2016
Longlands Farm, Rush Wall Lanewind turbinewind turbine3.5operationalupdated Feb 2024May 2018—Feb 2024
North Court Farm, Redwickwind turbinewind turbine3.5application submitted may be out of dateupdated Aug 2023Jul 2023—Aug 2023
Langstone Court Road Solar Farmsolar farmsolar farm2.5operationalupdated Jun 2013Mar 2011granted Nov 2011Jun 2013
Nash Waste Water Treatment Works Turbinewind turbinewind turbine2.5operationalupdated Jul 2017Dec 2011granted Jul 2012Jul 2017
Docks Way Solar Farmsolar farmsolar farm2.4approved, not builtupdated Dec 2021Mar 2021granted Dec 2021Dec 2021
ANP Newport Wind Turbinewind farmwind farm2.3operationalupdated Oct 2016Jul 2015granted Sep 2015Oct 2016
Clearwell Farm solarsolar farmsolar farm2operationalupdated Sep 2016Apr 2011granted May 2011Sep 2016
New Venture Buildings, Caswell Wayrooftop solarrooftop solar1.8approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023
Docks Waysolar farmsolar farm1approved, not builtupdated Aug 2024Jan 2023granted Aug 2024Aug 2024
Docks Way Disposal Site, Docks Waybattery storagebattery storage1approved, not builtupdated Mar 2026Nov 2025granted Feb 2026Mar 2026
Smaller schemes under 1 MW, mostly rooftop solar (11)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Celtic Way, Celtic Lakesrooftop solarrooftop solar0.3approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024
Began Road - Ground Mounted Solar Pv arraysolar farmsolar farm0.2application withdrawnupdated Mar 2022Feb 2022—Mar 2022
Hasbro Bradley UK, Caswell Wayrooftop solarrooftop solar0.1approved, not builtupdated Oct 2024Sep 2024granted Oct 2024Oct 2024
Llanwern Solar Farm & Battery Storagebattery storagebattery storage—operationalupdated Mar 2022Feb 2018granted Apr 2019Mar 2022
Wentlooge Renewable Energy Hubbattery storagebattery storage—appeal lodged may be out of dateupdated Feb 2024Jun 2022—Feb 2024
Geraint Thomas National Velodrome Solarrooftop solarrooftop solar—operationalupdated May 2022——May 2022
Craig y Perthi Solar Farmbattery storagebattery storage—refusedupdated Jan 2026Apr 2024refused Oct 2025Jan 2026
Kingsway Multi Storey Car Park, Newport, South Walesrooftop solarrooftop solar—no application requiredupdated Feb 2024——Feb 2024
Imperial Parkrooftop solarrooftop solar—no application requiredupdated Nov 2023——Nov 2023
Uskmouth Power Station, West Nash Roadbattery storagebattery storage—approved, not builtupdated Nov 2025May 2025granted Oct 2025Nov 2025
Abertillery Wind farm - Batterybattery storagebattery storage—application submittedupdated Dec 2024Oct 2024—Dec 2024

Postcode districts in Newport

DistrictProjects within 10 kmPendingApprovedOperational
NP104151614
NP184471312
NP194281313
NP203951313

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Newport by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.