Uskmouth Power Station (230 MW battery storage)

Uskmouth Power Station is a 230 MW battery storage project in Newport, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 November 2023; the record was last updated on 3 February 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

230 MWbattery storage
under constructionstatus in REPD
3 February 2025record last updated
Newportcouncil area

Planning timeline

DateStage
31 August 2022Application submitted
7 December 2022Refused by the planning authority
7 December 2022Planning permission granted
1 November 2023Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
230 MW
Status (REPD)
under construction
Record last updated
3 February 2025
Operator or applicant
Simec Atlantic Energy Uskmouth Power Station
Planning authority
Newport
Planning application reference
22/0823
Address (REPD)
Uskmouth Power Station West Nash Road Nash Newport
Council area (by location)
Newport
Time to decision
14 weeks
Name in REPD
Uskmouth Power Station - Battery Storage
REPD reference
10936

Who decides

ApplicationsNewportUK
Decided applications (solar, wind, battery)2210,236
Refused5 (23%)19%
Solar refused4 of 1312%
Onshore wind refused0 of 345%
Battery storage refused1 of 616%
Median time from submission to decision20.4 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Uskmouth Power Station, West Nash Roadbattery storage120under construction0.8
Solutia UK Ltdwind farm5operational2.2
Traston Roadbattery storage20operational2.5
Leeway House, Leeway Industrial Estatebattery storage20.6approved, not built2.6
Llanwern Solar Farm & Battery Storagesolar farm75operational3.5
Craig y Perthi Solar Farmsolar farm99.9refused6.0
Wentlooge Renewable Energy Hubsolar farm125appeal lodged6.9
Rush Wall Solar Parksolar farm75appeal lodged7.0
Abertillery Wind farmwind farm39.6application submitted7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5485, -2.9492).