Energy Projects Near You

Rush Wall Solar Park (75 MW)

Rush Wall Solar Park is a 75 MW solar farm project in Newport, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused; appeal lodged on 8 February 2024; the record was last updated on 13 February 2024. It is decided by the Welsh Government as a development of national significance. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

75 MWsolar farm
appeal lodgedmay be out of datestatus in REPD
13 February 2024record last updated
Newportcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
18 March 2022Application submitted
8 February 2024Appeal lodged

Project details

Technology
solar farm
Capacity
75 MW
Status (REPD)
appeal lodged
Record last updated
13 February 2024
Operator or applicant
Rush Wall Solar Park
Planning authority
Welsh Government (NSIP)
Planning application reference
DNS/3220457
Site area
85.0 ha
Address (REPD)
Land near Redwick, SE of Newport
Council area (by location)
Newport
REPD reference
7194

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Abertillery Wind farmwind farm39.6application submitted1.5
Llanwern Solar Farm & Battery Storagesolar farm75operational3.9
Land North West of Magor Service Stationsolar farm5abandoned4.0
Craig y Perthi Solar Farmsolar farm99.9refused4.5
Court Farmsolar farm8.5operational5.8
Uskmouth Power Stationbattery storage230under construction7.0
Leeway House, Leeway Industrial Estatebattery storage20.6approved, not built7.3
Uskmouth Power Station, West Nash Roadbattery storage120under construction7.8
Solutia UK Ltdwind farm5operational8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5522, -2.8481).