Energy Projects Near You

Llanwern Solar Farm & Battery Storage (75 MW)

Llanwern Solar Farm & Battery Storage is a 75 MW solar farm project in Newport, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2021; the record was last updated on 31 March 2022. It is decided by the Welsh Government as a development of national significance.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

75 MWsolar farm
operationalstatus in REPD
31 March 2022record last updated
Newportcouncil area

Planning timeline

DateStage
20 February 2018Application submitted
13 November 2018Planning permission granted
1 June 2020Construction started
1 March 2021Operational

Project details

Technology
solar farm
Capacity
75 MW
Status (REPD)
operational
Record last updated
31 March 2022
Operator or applicant
NextEnergy Capital LLP
Planning authority
Welsh Government (NSIP)
Planning application reference
DNS/3213968
Site area
121.4 ha
Address (REPD)
S/o Whitson Electricity Substa, Broad Street Common, Nash, Newport,
Council area (by location)
Newport
Time to decision
38 weeks
REPD reference
6411

The scheme also includes battery storage, recorded separately in REPD (operational).

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Craig y Perthi Solar Farmsolar farm99.9refused2.9
Leeway House, Leeway Industrial Estatebattery storage20.6approved, not built3.3
Uskmouth Power Stationbattery storage230under construction3.5
Rush Wall Solar Parksolar farm75appeal lodged3.9
Abertillery Wind farmwind farm39.6application submitted4.0
Solutia UK Ltdwind farm5operational4.2
Uskmouth Power Station, West Nash Roadbattery storage120under construction4.3
Traston Roadbattery storage20operational4.5
Court Farmsolar farm8.5operational4.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5613, -2.9032).