Craig y Perthi Solar Farm (99.9 MW)

Craig y Perthi Solar Farm is a 99.9 MW solar farm project in Newport, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 21 October 2025; the record was last updated on 19 January 2026. It is decided by the Welsh Government as a development of national significance.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99.9 MWsolar farm
refusedstatus in REPD
19 January 2026record last updated
Newportcouncil area

Planning timeline

DateStage
11 April 2024Application submitted
21 October 2025Refused by the planning authority

Project details

Technology
solar farm
Capacity
99.9 MW
Status (REPD)
refused
Record last updated
19 January 2026
Operator or applicant
JBM Solar Projects Limited
Planning authority
Welsh Government (NSIP)
Planning application reference
DNS/3279787
Site area
240.0 ha
Address (REPD)
Btw M4 and the Railway, Near Llanwern, Underwood & Bishston, Newport
Council area (by location)
Newport
Time to decision
80 weeks
REPD reference
12997

The scheme also includes battery storage, recorded separately in REPD (refused).

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Court Farmsolar farm8.5operational1.9
Llanwern Solar Farm & Battery Storagesolar farm75operational2.9
Land North West of Magor Service Stationsolar farm5abandoned3.4
Abertillery Wind farmwind farm39.6application submitted3.5
Rush Wall Solar Parksolar farm75appeal lodged4.5
Leeway House, Leeway Industrial Estatebattery storage20.6approved, not built4.6
Solutia UK Ltdwind farm5operational5.7
Traston Roadbattery storage20operational5.9
Uskmouth Power Stationbattery storage230under construction6.0