Energy Projects Near You

Solar, wind and battery projects near Caldicot (NP26)

23 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NP26 (Monmouthshire): 4 are waiting for a planning decision, 1 approved but not yet running, 11 operational. The largest live scheme is Rush Wall Solar Park (75 MW solar farm, refused; appeal lodged on 8 February 2024; REPD status may be out of date), 6.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23projects within 10 km
4awaiting a decision
1approved, not running
11operational

Projects within 10 km of NP26

Projects of 1 MW and more (20)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Great House Farmwind farmwind farm3application withdrawnupdated Nov 2016Oct 2012—Nov 2016Monmouthshire1.8
Southbrook Solar Farmsolar farmsolar farm5operationalupdated Jun 2016Jul 2015granted Dec 2015Jun 2016Monmouthshire3.9
Land North West of Magor Service Stationsolar farmsolar farm5abandonedupdated Dec 2016May 2015granted Dec 2015Dec 2016Monmouthshire4.0
Magor Breweryrooftop solarrooftop solar1.7abandonedupdated Jan 2020Sep 2015granted Oct 2015Jan 2020Monmouthshire4.6
Oak Grove Farmsolar farmsolar farm5.7operationalupdated Nov 2017Mar 2015—Nov 2017Monmouthshire4.6
Longlands Farm, Rush Wall Lanewind turbinewind turbine3.5operationalupdated Feb 2024May 2018—Feb 2024Newport5.3
Abertillery Wind farmwind farmwind farm39.6application submittedupdated Dec 2024Oct 2024—Dec 2024Newport5.4
Rhewl Farmsolar farmsolar farm6operationalupdated Jul 2016Aug 2014granted Jun 2015Jul 2016Monmouthshire5.8
North Court Farm, Redwickwind turbinewind turbine3.5application submitted may be out of dateupdated Aug 2023Jul 2023—Aug 2023Newport6.4
Rush Wall Solar Parksolar farmsolar farm75appeal lodged may be out of dateupdated Feb 2024Mar 2022—Feb 2024Newport6.4
Court Farmsolar farmsolar farm8.5operationalupdated Oct 2017Mar 2015granted Oct 2015Oct 2017Newport7.0
Craig y Perthi Solar Farmsolar farmsolar farm99.9refusedupdated Jan 2026Apr 2024refused Oct 2025Jan 2026Newport7.4
Land adjacent to Church Roadsolar farmsolar farm3.5operationalupdated Jun 2016Apr 2015granted Sep 2015Jun 2016South Gloucestershire9.0
Buckwell Farm Solar Parksolar farmsolar farm8.1abandonedupdated Dec 2019Oct 2013granted Aug 2014Dec 2019Monmouthshire9.1
Llanwern Solar Farm & Battery Storagesolar farmsolar farm75operationalupdated Mar 2022Feb 2018granted Nov 2018Mar 2022Newport9.2
Langstone Court Road Solar Farmsolar farmsolar farm2.5operationalupdated Jun 2013Mar 2011granted Nov 2011Jun 2013Newport9.2
Avonmouth Port IIwind farmwind farm5operationalupdated Mar 2014Aug 2008granted Jan 2009Mar 2014South Gloucestershire9.4
Severn Roadwind turbinewind turbine4.2operationalupdated Feb 2024Mar 2020granted Feb 2021Feb 2024Bristol9.4
Unnamed battery storage (REPD 6907)battery storagebattery storage20abandonedupdated Mar 2019Aug 2016—Mar 2019Bristol9.9
Avonmouth Portwind farmwind farm6operationalupdated Sep 2007Aug 2005granted Dec 2005Sep 2007Bristol9.9
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Abertillery Wind farm - Batterybattery storagebattery storage—application submittedupdated Dec 2024Oct 2024—Dec 2024Newport5.4
Craig y Perthi Solar Farmbattery storagebattery storage—refusedupdated Jan 2026Apr 2024refused Oct 2025Jan 2026Newport7.4
Newhouse Farm Industrial Estate, Unit 1rooftop solarrooftop solar0.3approved, not builtupdated Mar 2026Dec 2025granted Jan 2026Mar 2026Monmouthshire7.8

Distance from the average position of the NP26 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm11107175
Rooftop solar201000.3
Wind farm4102039.6
Wind turbine310203.5
Battery storage310010

MW in pipeline: pending, approved and under-construction capacity.

How Monmouthshire decides solar, wind and battery applications

ApplicationsMonmouthshireUK
Decided applications (solar, wind, battery)1210,236
Refused2 (17%)19%
Solar refused2 of 1212%
Median time from submission to decision19.1 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Monmouthshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NP26, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.