Energy Projects Near You

Southbrook Solar Farm (5 MW)

Southbrook Solar Farm is a 5 MW solar farm project in Monmouthshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 May 2016; the record was last updated on 14 June 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
14 June 2016record last updated
Monmouthshirecouncil area

Planning timeline

DateStage
13 July 2015Application submitted
3 December 2015Planning permission granted
15 February 2016Construction started
15 May 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
14 June 2016
Operator or applicant
Sunventures (Suncredit UK)
Planning authority
Monmouthshire
Planning application reference
DC/2015/00855
Site area
10.0 ha
Address (REPD)
Southbrook Farm, Sudbrook Road, Sudbrook, Portskewett, Caldicot, Gwent
Council area (by location)
Monmouthshire
Time to decision
20 weeks
REPD reference
5379

Who decides

ApplicationsMonmouthshireUK
Decided applications (solar, wind, battery)1210,236
Refused2 (17%)19%
Solar refused2 of 1212%
Median time from submission to decision19.1 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Oak Grove Farmsolar farm5.7operational2.6
Rhewl Farmsolar farm6operational5.2
Avonmouth Port IIwind farm5operational6.4
Unnamed battery storage (REPD 6907)battery storage20abandoned7.0
Central Park Solar Farm & Battery Storagesolar farm7application submitted7.4
Sedbury Parksolar farm5operational7.4
Land North West of Magor Service Stationsolar farm5abandoned7.8
Severn Road, Hallenbattery storage70approved, not built7.8
Tump Solar Farmsolar farm5operational8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5873, -2.7227).