Penpergwm Solar Farm (Great House Farm) (32 MW)

Penpergwm Solar Farm (Great House Farm) is a 32 MW solar farm project in Monmouthshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 August 2025; the record was last updated on 24 April 2026. It is decided by the Welsh Government as a development of national significance.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32 MWsolar farm
under constructionstatus in REPD
24 April 2026record last updated
Monmouthshirecouncil area

Planning timeline

DateStage
25 January 2022Application submitted
17 January 2023Planning permission granted
1 August 2025Construction started

Project details

Technology
solar farm
Capacity
32 MW
Status (REPD)
under construction
Record last updated
24 April 2026
Operator or applicant
Renewable Connections Developments Limited / European Energy UK Ltd
Planning authority
Welsh Government (NSIP)
Planning application reference
DNS/3252305
Site area
70.2 ha
Address (REPD)
Great House Farm, Abergavenny
Council area (by location)
Monmouthshire
Time to decision
51 weeks
Contracts for Difference
AR6
REPD reference
10035

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Manor Farm (Monmouthshire)solar farm10.5operational5.3
Land at Lower House Farmsolar farm8.1operational7.3
Mamhilad Solar Farmsolar farm5operational9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7975, -2.9736).