Manor Farm (Monmouthshire) (10.5 MW solar farm)

Manor Farm (Monmouthshire) is a 10.5 MW solar farm project in Monmouthshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 June 2016; the record was last updated on 22 September 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.5 MWsolar farm
operationalstatus in REPD
22 September 2016record last updated
Monmouthshirecouncil area

Planning timeline

DateStage
7 January 2013Application submitted
13 September 2013Refused by the planning authority
4 April 2014Appeal lodged
24 October 2014Planning permission granted
24 October 2014Appeal allowed
18 April 2016Construction started
23 June 2016Operational

Project details

Technology
solar farm
Capacity
10.5 MW
Status (REPD)
operational
Record last updated
22 September 2016
Operator or applicant
3C Energy/Conergy
Planning authority
Monmouthshire
Planning application reference
DC/2013/00006
Appeal reference
APP/E6840/A/14/2212987
Site area
27.0 ha
Address (REPD)
Llanvapley, Monmouthshire
Council area (by location)
Monmouthshire
Time to decision
94 weeks
REPD reference
1746

Who decides

ApplicationsMonmouthshireUK
Decided applications (solar, wind, battery)1210,236
Refused2 (17%)19%
Solar refused2 of 1212%
Median time from submission to decision19.1 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Penpergwm Solar Farm (Great House Farm)solar farm32under construction5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8346, -2.9253).