Nibley Mill Farm (15.9 MW solar farm)

Nibley Mill Farm is a 15.9 MW solar farm project in Forest of Dean, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 10 September 2014; the record was last updated on 16 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15.9 MWsolar farm
refusedstatus in REPD
16 September 2014record last updated
Forest of Deancouncil area

Planning timeline

DateStage
28 May 2014Application submitted
10 September 2014Refused by the planning authority

Project details

Technology
solar farm
Capacity
15.9 MW
Status (REPD)
refused
Record last updated
16 September 2014
Operator or applicant
AEE Renewables
Planning authority
Forest of Dean
Planning application reference
P0871/14/FUL
Address (REPD)
Land At Lydney Gloucestershire GL15 4LN
Council area (by location)
Forest of Dean
Time to decision
15 weeks
REPD reference
2310

Who decides

ApplicationsForest of DeanUK
Decided applications (solar, wind, battery)2810,236
Refused8 (29%)19%
Solar refused7 of 2612%
Battery storage refused1 of 216%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hurst Farmsolar farm5operational1.5
Yorkley Solar Parksolar farm5operational2.2
Watts Group Factory Sitebattery storage10abandoned3.7
Solar Panels at Ne/O Poulton Court Farmsolar farm40application submitted4.3
Hook Street Energy Storage Compoundbattery storage100refused5.5
Northington Lanebattery storage35approved, not built6.1
Awre Penisular Farmer's Community Solar Schemesolar farm49.9refused6.8
Woodlands Farm, Clapton - Ground Mounted Solar Parksolar farm36approved, not built6.9
Worlds End Solar Farmsolar farm49.9application submitted7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7418, -2.5044).