Hurst Farm (5 MW solar farm)

Hurst Farm is a 5 MW solar farm project in Forest of Dean, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 May 2014; the record was last updated on 27 November 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
27 November 2014record last updated
Forest of Deancouncil area

Planning timeline

DateStage
9 September 2013Application submitted
15 November 2013Planning permission granted
6 January 2014Construction started
19 May 2014Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
27 November 2014
Operator or applicant
Bee Green Solar
Planning authority
Forest of Dean
Planning application reference
P1358/13/FUL
Site area
15.0 ha
Address (REPD)
Hurst Farm, Cross Hands, Lydney, Gloucestershire
Council area (by location)
Forest of Dean
Time to decision
10 weeks
REPD reference
1489

Who decides

ApplicationsForest of DeanUK
Decided applications (solar, wind, battery)2810,236
Refused8 (29%)19%
Solar refused7 of 2612%
Battery storage refused1 of 216%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nibley Mill Farmsolar farm15.9refused1.5
Watts Group Factory Sitebattery storage10abandoned2.5
Yorkley Solar Parksolar farm5operational2.7
Hook Street Energy Storage Compoundbattery storage100refused4.4
Solar Panels at Ne/O Poulton Court Farmsolar farm40application submitted5.4
Woodlands Farm, Clapton - Ground Mounted Solar Parksolar farm36approved, not built5.5
Worlds End Solar Farmsolar farm49.9application submitted6.0
Northington Lanebattery storage35approved, not built7.3
Hill Court Solar farm & Battery storagebattery storage35approved, not built7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7286, -2.5074).