Solar, wind and battery projects near Newent (GL18)
14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL18 (Forest of Dean): 2 are waiting for a planning decision, 3 approved but not yet running, 6 operational. The largest live scheme is Moat Farm Solar Farm (49.9 MW solar farm, approved on 19 May 2026, not yet built), 3.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of GL18
Projects of 1 MW and more (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Moat Farm Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Jun 2026 | Jan 2022 | granted May 2026 | Jun 2026 | Forest of Dean | 3.0 |
| Land At Rymes Farm (Phase 2)/Grange Solar Farmsolar farm | solar farm | 6.8 | operationalupdated Sep 2016 | Dec 2014 | granted Jun 2015 | Sep 2016 | Forest of Dean | 3.6 |
| Stream Lane, Upleadon Solar Photovoltaic Farmsolar farm | solar farm | 6 | refusedupdated Aug 2023 | Oct 2022 | refused Jul 2023 | Aug 2023 | Forest of Dean | 3.7 |
| Land At Rymes Farm (Phase 1)solar farm | solar farm | 6.9 | operationalupdated Jul 2016 | Dec 2014 | granted Jun 2015 | Jul 2016 | Forest of Dean | 3.9 |
| Highleadon Solar Arrays & Battery Storagesolar farm | solar farm | 49.9 | operationalupdated Apr 2026 | Feb 2022 | granted Oct 2023 | Apr 2026 | Forest of Dean | 6.0 |
| Murrells End Farm Solar Arrayssolar farm | solar farm | 49.9 | refusedupdated Jun 2022 | Jun 2022 | refused Mar 2023 | Jun 2022 | Forest of Dean | 8.6 |
| Vantage Point Business Parksolar farm | solar farm | 3.6 | refusedupdated Mar 2015 | Jan 2015 | refused Mar 2015 | Mar 2015 | Forest of Dean | 9.0 |
| Vantage Pointrooftop solar | rooftop solar | 1.4 | operationalupdated Mar 2016 | May 2011 | granted Jun 2011 | Mar 2016 | Forest of Dean | 9.5 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Highleadon Solar Arrays & Battery Storagebattery storage | battery storage | — | operationalupdated Apr 2026 | Feb 2022 | granted Oct 2023 | Apr 2026 | Forest of Dean | 6.0 |
| Chessgrove Farm, Chessgrove Lane Solar Arraysrooftop solar | rooftop solar | — | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Forest of Dean | 8.5 |
| Siddington Farm, Orlham Lanesolar farm | solar farm | — | application submitted may be out of dateupdated Nov 2022 | Oct 2022 | — | Nov 2022 | Herefordshire | 8.8 |
| Leewayssolar farm | solar farm | 0.5 | operationalupdated Nov 2019 | Oct 2018 | granted Jan 2019 | Nov 2019 | Forest of Dean | 8.9 |
| Grove Farm - Microgrid of Solar Panelssolar farm | solar farm | — | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | Malvern Hills | 9.5 |
| The Farm Consultancy Grouprooftop solar | rooftop solar | — | approved, not builtupdated Nov 2025 | Jul 2025 | granted Sep 2025 | Nov 2025 | Tewkesbury | 9.8 |
Distance from the average position of the GL18 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 2 | 1 | 4 | 3 | 49.9 |
| Rooftop solar | 3 | 0 | 2 | 1 | 0 | 0 |
| Battery storage | 1 | 0 | 0 | 1 | 0 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Forest of Dean decides solar, wind and battery applications
| Applications | Forest of Dean | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 28 | 10,236 |
| Refused | 8 (29%) | 19% |
| Solar refused | 7 of 26 | 12% |
| Battery storage refused | 1 of 2 | 16% |
| Median time from submission to decision | 14.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 1 | — |
All projects in Forest of Dean
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GL18, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.