Murrells End Farm Solar Arrays (49.9 MW)

Murrells End Farm Solar Arrays is a 49.9 MW solar farm project in Forest of Dean, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 15 March 2023; the record was last updated on 17 June 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
refusedstatus in REPD
17 June 2022record last updated
Forest of Deancouncil area

Planning timeline

DateStage
1 June 2022Application submitted
15 March 2023Refused by the planning authority

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
refused
Record last updated
17 June 2022
Operator or applicant
Elgin Energy EsCo Limited
Planning authority
Forest of Dean
Planning application reference
P0271/22/FUL
Site area
73.1 ha
Address (REPD)
The South Of Murrells End Farm Murrells End Hartpury
Council area (by location)
Forest of Dean
Time to decision
41 weeks
Name in REPD
Murrells End Farm - Solar Arrays
REPD reference
11484

Who decides

ApplicationsForest of DeanUK
Decided applications (solar, wind, battery)2810,236
Refused8 (29%)19%
Solar refused7 of 2612%
Battery storage refused1 of 216%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lassington Lane, Highnambattery storage10application submitted1.8
Lassington Lane, Highnam Solar Farmsolar farm40application submitted1.8
Maisemore Solar Farmsolar farm37approved, not built2.4
Highnam Solar Farmsolar farm5abandoned2.4
Highleadon Solar Arrays & Battery Storagesolar farm49.9operational2.7
Two Mile Lane, Highnam Solar Farmsolar farm36application submitted2.7
Linton Court Farm, Highnambattery storage99.9approved, not built3.6
Over Farmsolar farm9.9approved, not built3.7
Bengrove Farm, Base Lane Solar Farmsolar farm15approved, not built4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8998, -2.3083).