Energy Projects Near You

Highnam Solar Farm (5 MW)

Highnam Solar Farm is a 5 MW solar farm project in Tewkesbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 14 November 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
14 November 2019record last updated
Tewkesburycouncil area

Planning timeline

DateStage
16 June 2015Application submitted
24 November 2015Refused by the planning authority
22 January 2016Appeal lodged
6 June 2016Planning permission granted
6 June 2016Appeal allowed
6 June 2019Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
14 November 2019
Operator or applicant
Pike Solar
Planning authority
Tewkesbury
Planning application reference
15/00410/FUL
Appeal reference
APP/G1630/W/16/3141634
Site area
22.8 ha
Address (REPD)
Land At Highnam Farm, Two Mile Lane, Highnam, Gloucester, Gloucestershire
Council area (by location)
Tewkesbury
Time to decision
51 weeks
REPD reference
5452

Who decides

ApplicationsTewkesburyUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2712%
Battery storage refused0 of 416%
Median time from submission to decision25.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Two Mile Lane, Highnam Solar Farmsolar farm36application submitted0.3
Lassington Lane, Highnambattery storage10application submitted0.9
Lassington Lane, Highnam Solar Farmsolar farm40application submitted0.9
Linton Court Farm, Highnambattery storage99.9approved, not built1.5
Maisemore Solar Farmsolar farm37approved, not built2.2
Over Farmsolar farm9.9approved, not built2.2
Murrells End Farm Solar Arrayssolar farm49.9refused2.4
Sudmeadow Road, Hempstedbattery storage50approved, not built3.7
Highleadon Solar Arrays & Battery Storagesolar farm49.9operational4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8778, -2.3069).