Energy Projects Near You

Maisemore Solar Farm (37 MW)

Maisemore Solar Farm is a 37 MW solar farm project in Tewkesbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 March 2023, not yet built; the record was last updated on 1 June 2023. REPD records the planning permission as expiring on 6 March 2026, but the project holds a Contracts for Difference award (AR6), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

37 MWsolar farm
approved, not builtmay be out of datestatus in REPD
1 June 2023record last updated
Tewkesburycouncil area

REPD records the planning permission as expiring on 6 March 2026, but the project holds a Contracts for Difference award (AR6), so construction may have started.

Planning timeline

DateStage
19 April 2022Application submitted
6 March 2023Planning permission granted
6 March 2026Permission expired

Project details

Technology
solar farm
Capacity
37 MW
Status (REPD)
approved, not built
Record last updated
1 June 2023
Operator or applicant
Renewable Connections Developments Limited
Planning authority
Tewkesbury
Planning application reference
22/00397/FUL
Site area
58.0 ha
Address (REPD)
South Of Maisemore
Council area (by location)
Tewkesbury
Time to decision
46 weeks
Contracts for Difference
AR6
Name in REPD
Maisemore - Solar Farm
REPD reference
11170

Who decides

ApplicationsTewkesburyUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2712%
Battery storage refused0 of 416%
Median time from submission to decision25.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lassington Lane, Highnambattery storage10application submitted1.4
Lassington Lane, Highnam Solar Farmsolar farm40application submitted1.4
Over Farmsolar farm9.9approved, not built1.5
Linton Court Farm, Highnambattery storage99.9approved, not built2.0
Highnam Solar Farmsolar farm5abandoned2.2
Two Mile Lane, Highnam Solar Farmsolar farm36application submitted2.4
Murrells End Farm Solar Arrayssolar farm49.9refused2.4
Bengrove Farm, Base Lane Solar Farmsolar farm15approved, not built2.8
Bengrove Farm, Base Lanebattery storage49.9application submitted2.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8871, -2.2793).