Energy Projects Near You

Bengrove Farm, Base Lane (49.9 MW battery storage)

Bengrove Farm, Base Lane is a 49.9 MW battery storage project in Tewkesbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 15 November 2022, no decision recorded; the record was last updated on 12 December 2022. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
application submittedmay be out of datestatus in REPD
12 December 2022record last updated
Tewkesburycouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
15 November 2022Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
12 December 2022
Operator or applicant
Bengrove Bess Limited
Planning authority
Tewkesbury
Planning application reference
22/01231/FUL
Address (REPD)
Bengrove Farm, Base Lane, Sandhurst
Council area (by location)
Tewkesbury
Name in REPD
Bengrove Farm, Base Lane - Battery Storage
REPD reference
12830

Who decides

ApplicationsTewkesburyUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2712%
Battery storage refused0 of 416%
Median time from submission to decision25.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bengrove Farm, Base Lane Solar Farmsolar farm15approved, not built<0.1
Solar Array at W/O Twigworth And E/O Coxs Brooksolar farm16approved, not built1.5
Maisemore Solar Farmsolar farm37approved, not built2.8
Over Farmsolar farm9.9approved, not built3.7
Lassington Lane, Highnambattery storage10application submitted4.1
Lassington Lane, Highnam Solar Farmsolar farm40application submitted4.1
Murrells End Farm Solar Arrayssolar farm49.9refused4.2
Registry Twyver House, Bruton Wayrooftop solar8.8application withdrawn4.3
Linton Court Farm, Highnambattery storage99.9approved, not built4.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9031, -2.2475).