Solar Array at W/O Twigworth And E/O Coxs Brook (16 MW)

Solar Array at W/O Twigworth And E/O Coxs Brook is a 16 MW solar farm project in Tewkesbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 April 2024, not yet built; the record was last updated on 16 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWsolar farm
approved, not builtstatus in REPD
16 February 2026record last updated
Tewkesburycouncil area

Planning timeline

DateStage
3 May 2023Application submitted
24 April 2024Planning permission granted
24 April 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
16 MW
Status (REPD)
approved, not built
Record last updated
16 February 2026
Operator or applicant
PS Renewables Limited
Planning authority
Tewkesbury
Planning application reference
23/00441/FUL
Address (REPD)
W/O Twigworth And E/O Coxs Brook, Twigworth, Gloucester
Council area (by location)
Tewkesbury
Time to decision
51 weeks
Contracts for Difference
AR7a
Name in REPD
Cox's Brook Solar Farm - Solar Array
REPD reference
13966

Who decides

ApplicationsTewkesburyUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2712%
Battery storage refused0 of 416%
Median time from submission to decision25.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bengrove Farm, Base Lane Solar Farmsolar farm15approved, not built1.5
Bengrove Farm, Base Lanebattery storage49.9application submitted1.5
Registry Twyver House, Bruton Wayrooftop solar8.8application withdrawn3.5
Maisemore Solar Farmsolar farm37approved, not built3.5
Over Farmsolar farm9.9approved, not built3.9
Sudmeadow Road, Hempstedbattery storage50approved, not built4.4
Lassington Lane, Highnam Solar Farmsolar farm40application submitted4.9
Lassington Lane, Highnambattery storage10application submitted4.9
Linton Court Farm, Highnambattery storage99.9approved, not built4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8955, -2.2299).