Energy Projects Near You

Land At Rymes Farm (Phase 2)/Grange Solar Farm (6.8 MW)

Land At Rymes Farm (Phase 2)/Grange Solar Farm is a 6.8 MW solar farm project in Forest of Dean, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 November 2015; the record was last updated on 20 September 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.8 MWsolar farm
operationalstatus in REPD
20 September 2016record last updated
Forest of Deancouncil area

Planning timeline

DateStage
23 December 2014Application submitted
12 June 2015Planning permission granted
15 August 2015Construction started
15 November 2015Operational

Project details

Technology
solar farm
Capacity
6.8 MW
Status (REPD)
operational
Record last updated
20 September 2016
Operator or applicant
Solar Century (TGC Renewables)
Planning authority
Forest of Dean
Planning application reference
P1976/14/FUL
Site area
13.8 ha
Address (REPD)
Land At Rymes Farm, Malswick, Newent, Gloucestershire
Council area (by location)
Forest of Dean
Time to decision
24 weeks
REPD reference
4943

Who decides

ApplicationsForest of DeanUK
Decided applications (solar, wind, battery)2810,236
Refused8 (29%)19%
Solar refused7 of 2612%
Battery storage refused1 of 216%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land At Rymes Farm (Phase 1)solar farm6.9operational0.2
Moat Farm Solar Farmsolar farm49.9approved, not built1.1
Stream Lane, Upleadon Solar Photovoltaic Farmsolar farm6refused1.9
Highleadon Solar Arrays & Battery Storagesolar farm49.9operational2.4
Murrells End Farm Solar Arrayssolar farm49.9refused5.0
Lassington Lane, Highnam Solar Farmsolar farm40application submitted6.5
Lassington Lane, Highnambattery storage10application submitted6.5
Highnam Solar Farmsolar farm5abandoned6.6
Two Mile Lane, Highnam Solar Farmsolar farm36application submitted6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.92, -2.3737).