Renewable energy projects in Herefordshire

37 solar, wind or battery projects of 150 kW or more are located in Herefordshire (REPD, July 2026 extract): 1 pending, 19 approved but not running, 6 operational and 6 refused. The council refused 6 of 35 decided applications (17%; UK 19%), with a median 13 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

37projects in the council area
1awaiting a decision
19approved, not running
17%of decisions refused

How Herefordshire decides

ApplicationsHerefordshireUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused6 of 2712%
Onshore wind refused0 of 145%
Battery storage refused0 of 716%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

Projects in Herefordshire

Projects of 1 MW and more (17)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Peterstow Gas Compressor Station, Hentlandbattery storagebattery storage49.9approved, not builtupdated Jun 2026May 2023granted Mar 2025Jun 2026
Larport, Clay Hill Pit Solar Photovoltaics & Battery storagesolar farmsolar farm45operationalupdated Jul 2024Oct 2021granted May 2022Jul 2024
Westhide Solar Farmsolar farmsolar farm34.6abandonedupdated Feb 2022Dec 2021granted Mar 2023Feb 2022
Oatcroft Fram, Titleysolar farmsolar farm30refusedupdated Apr 2024Dec 2023refused Mar 2024Apr 2024
Frome Valley Solar Farmsolar farmsolar farm20.6approved, not builtupdated Feb 2026Jun 2024granted Jul 2025Feb 2026
Land to the west of Clay Hill Pit / Larport Farmbattery storagebattery storage20operationalupdated Jan 2020Aug 2016—Jan 2020
Perserverance Roadbattery storagebattery storage20approved, not built may be out of dateupdated Mar 2023Mar 2020granted Nov 2020Mar 2023
Sinton End Farm, Acton Beauchamp Solar Farmsolar farmsolar farm20refusedupdated Dec 2025Jul 2025refused Oct 2025Dec 2025
Little Frome Farmsolar farmsolar farm16.1refused on appealupdated May 2016Jun 2015refused Sep 2015May 2016
Reeves Hillwind farmwind farm9.2permission expiredupdated May 2016May 2008granted Sep 2011May 2016
Witches Solar Farmsolar farmsolar farm5operationalupdated May 2014Nov 2010granted Feb 2011May 2014
Lower Venn Farmsolar farmsolar farm5operationalupdated Aug 2016Aug 2015granted Nov 2015Aug 2016
Brookhouse Farmsolar farmsolar farm5refused on appealupdated Sep 2016Aug 2015refused Nov 2015Sep 2016
Land at Green Farmsolar farmsolar farm1operationalupdated Jun 2016Jul 2015granted Sep 2015Jun 2016
Stocks House Farmsolar farmsolar farm1refused on appealupdated May 2016Mar 2015refused Jun 2015May 2016
Stretton Sugwas Solar Farmsolar farmsolar farm1application withdrawnupdated Mar 2020Jul 2016—Mar 2020
A J Lowther and Son Premisesolar farmsolar farm1under constructionupdated Jan 2022Aug 2019granted Oct 2020Jan 2022
Smaller schemes under 1 MW, mostly rooftop solar (20)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Lower Eggleton - Anaerobic Digestion Facilityrooftop solarrooftop solar0.7refusedupdated Jun 2026Sep 2022refused Dec 2025Jun 2026
Brierley Court Hop Farm, Brierley Lanerooftop solarrooftop solar0.6approved, not builtupdated Jan 2023Oct 2022granted Nov 2022Jan 2023
Bevisol Limited, Orchard Business Parkrooftop solarrooftop solar0.4approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024
Oakchurch Farm Shop, Staunton On Wyesolar farmsolar farm0.3approved, not builtupdated May 2024Mar 2024granted May 2024May 2024
Broomy Hill Water Treatment Workssolar farmsolar farm0.3permission expiredupdated Jul 2019Feb 2019granted Jul 2019Jul 2019
Manor Farm Solar Panelssolar farmsolar farm0.3under constructionupdated Jan 2021Dec 2020granted Feb 2021Jan 2021
Shobdon Poultry Farm, Shobdonsolar farmsolar farm0.3approved, not builtupdated May 2024Mar 2024granted May 2024May 2024
Elite Plastics, Twyford Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Sep 2022granted Dec 2022Dec 2022
Morrisons Supermarket - Photovoltaic Solar Panelsrooftop solarrooftop solar0.2approved, not builtupdated Jan 2023Oct 2022granted Nov 2022Jan 2023
Ridgehill WPSsolar farmsolar farm0.2permission expiredupdated Sep 2020Feb 2019granted Jun 2019Sep 2020
Green Spider Climbing, Ramsden Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Sep 2024May 2024granted Jul 2024Sep 2024
Chapel Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Nov 2025Jan 2025granted Mar 2025Nov 2025
Chapel Road - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026
Wye Valley Brewery, Panniers Lane To Cowarne Cottagesolar farmsolar farm0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026
Madley Nursery, Brampton Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023
Walford Saw Millsrooftop solarrooftop solar0.1approved, not builtupdated Sep 2021Mar 2021granted May 2021Sep 2021
Larport, Clay Hill Pit Solar Photovoltaics & Battery storagebattery storagebattery storage—operationalupdated Jan 2025Oct 2021granted May 2022Jan 2025
Siddington Farm, Orlham Lanesolar farmsolar farm—application submitted may be out of dateupdated Nov 2022Oct 2022—Nov 2022
The Hop Pocketsolar farmsolar farm—approved, not builtupdated Sep 2023Aug 2023granted Dec 2023Sep 2023
The Hop Pocketbattery storagebattery storage—approved, not builtupdated Sep 2023Aug 2023granted Dec 2023Sep 2023

Postcode districts in Herefordshire

DistrictProjects within 10 kmPendingApprovedOperational
HR119066
HR211062
HR30000
HR414072
HR53010
HR64040
HR76030
HR85140
HR98052
WR138041

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Herefordshire by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.