Energy Projects Near You

Solar, wind and battery projects near Malvern (WR13)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WR13 (Herefordshire): 4 approved but not yet running, 1 operational. The largest live scheme is Whitehouse Farm Energy Barn (40 MW battery storage, approved on 29 November 2017, not yet built), 5.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
4approved, not running
1operational

Projects within 10 km of WR13

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Havenwind turbinewind turbine1.2operationalupdated Sep 2005Dec 2002granted Feb 2003Sep 2005Malvern Hills4.3
Whitehouse Farm Energy Barnbattery storagebattery storage40approved, not builtupdated Jun 2020Oct 2017granted Nov 2017Jun 2020Malvern Hills5.8
Chapel Hill Solar Arrayssolar farmsolar farm49.9refusedupdated Dec 2025Jan 2025refused Nov 2025Dec 2025Malvern Hills7.4
Sinton End Farm, Acton Beauchamp Solar Farmsolar farmsolar farm20refusedupdated Dec 2025Jul 2025refused Oct 2025Dec 2025Herefordshire9.6
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Malvern Splash, Priory Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2024May 2024granted Jul 2024Aug 2024Malvern Hills2.2
Chapel Hillbattery storagebattery storage—refusedupdated Dec 2025Jan 2025refused Nov 2025Dec 2025Malvern Hills7.4
Bevisol Limited, Orchard Business Parkrooftop solarrooftop solar0.4approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024Herefordshire7.7
Millers Court Farm, Birts Streetrooftop solarrooftop solar0.2approved, not builtupdated Jun 2025Mar 2025granted May 2025Jun 2025Malvern Hills7.9

Distance from the average position of the WR13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm200020
Rooftop solar303000.8
Wind turbine100100
Battery storage2010140

MW in pipeline: pending, approved and under-construction capacity.

How Herefordshire decides solar, wind and battery applications

ApplicationsHerefordshireUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused6 of 2712%
Onshore wind refused0 of 145%
Battery storage refused0 of 716%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

All projects in Herefordshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.