Energy Projects Near You

Solar, wind and battery projects near Hereford (HR2)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of HR2 (Herefordshire): 6 approved but not yet running, 2 operational. The largest live scheme is Perserverance Road (20 MW battery storage, approved on 13 November 2020, not yet built; REPD status may be out of date), 8.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
0awaiting a decision
6approved, not running
2operational

Projects within 10 km of HR2

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land at Green Farmsolar farmsolar farm1operationalupdated Jun 2016Jul 2015granted Sep 2015Jun 2016Herefordshire1.4
Stretton Sugwas Solar Farmsolar farmsolar farm1application withdrawnupdated Mar 2020Jul 2016—Mar 2020Herefordshire7.3
Perserverance Roadbattery storagebattery storage20approved, not built may be out of dateupdated Mar 2023Mar 2020granted Nov 2020Mar 2023Herefordshire8.4
Witches Solar Farmsolar farmsolar farm5operationalupdated May 2014Nov 2010granted Feb 2011May 2014Herefordshire8.6
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ridgehill WPSsolar farmsolar farm0.2permission expiredupdated Sep 2020Feb 2019granted Jun 2019Sep 2020Herefordshire4.7
Madley Nursery, Brampton Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Herefordshire5.8
Broomy Hill Water Treatment Workssolar farmsolar farm0.3permission expiredupdated Jul 2019Feb 2019granted Jul 2019Jul 2019Herefordshire6.0
Elite Plastics, Twyford Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Sep 2022granted Dec 2022Dec 2022Herefordshire6.9
Green Spider Climbing, Ramsden Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Sep 2024May 2024granted Jul 2024Sep 2024Herefordshire7.2
Chapel Road - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Herefordshire7.9
Chapel Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Nov 2025Jan 2025granted Mar 2025Nov 2025Herefordshire8.2

Distance from the average position of the HR2 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm500200
Rooftop solar202000.4
Battery storage4040020.6

MW in pipeline: pending, approved and under-construction capacity.

How Herefordshire decides solar, wind and battery applications

ApplicationsHerefordshireUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused6 of 2712%
Onshore wind refused0 of 145%
Battery storage refused0 of 716%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

All projects in Herefordshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near HR2, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.