Little Frome Farm (16.1 MW solar farm)

Little Frome Farm is a 16.1 MW solar farm project in Herefordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 13 April 2016; the record was last updated on 4 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16.1 MWsolar farm
refused on appealstatus in REPD
4 May 2016record last updated
Herefordshirecouncil area

Planning timeline

DateStage
2 June 2015Application submitted
22 September 2015Refused by the planning authority
11 January 2016Appeal lodged
13 April 2016Appeal refused

Project details

Technology
solar farm
Capacity
16.1 MW
Status (REPD)
refused on appeal
Record last updated
4 May 2016
Operator or applicant
BE Renewables
Planning authority
Herefordshire, County of
Planning application reference
P151506/F
Appeal reference
APP/W1850/W/15/3140783
Address (REPD)
Little Frome, Linton Lane, Herefordshire, Bromyard
Council area (by location)
Herefordshire
Time to decision
16 weeks
REPD reference
5563

Who decides

ApplicationsHerefordshireUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused6 of 2712%
Onshore wind refused0 of 145%
Battery storage refused0 of 716%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sinton End Farm, Acton Beauchamp Solar Farmsolar farm20refused5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1792, -2.5097).