Little Frome Farm (16.1 MW solar farm)
Little Frome Farm is a 16.1 MW solar farm project in Herefordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 13 April 2016; the record was last updated on 4 May 2016.
16.1 MWsolar farm
refused on appealstatus in REPD
4 May 2016record last updated
Herefordshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 2 June 2015 | Application submitted |
| 22 September 2015 | Refused by the planning authority |
| 11 January 2016 | Appeal lodged |
| 13 April 2016 | Appeal refused |
Project details
- Technology
- solar farm
- Capacity
- 16.1 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 4 May 2016
- Operator or applicant
- BE Renewables
- Planning authority
- Herefordshire, County of
- Planning application reference
- P151506/F
- Appeal reference
- APP/W1850/W/15/3140783
- Address (REPD)
- Little Frome, Linton Lane, Herefordshire, Bromyard
- Council area (by location)
- Herefordshire
- Time to decision
- 16 weeks
- REPD reference
- 5563
Who decides
| Applications | Herefordshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 35 | 10,236 |
| Refused | 6 (17%) | 19% |
| Solar refused | 6 of 27 | 12% |
| Onshore wind refused | 0 of 1 | 45% |
| Battery storage refused | 0 of 7 | 16% |
| Median time from submission to decision | 13.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Sinton End Farm, Acton Beauchamp Solar Farm | solar farm | 20 | refused | 5.3 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1792, -2.5097).