Land to the west of Clay Hill Pit / Larport Farm (20 MW battery storage)

Land to the west of Clay Hill Pit / Larport Farm is a 20 MW battery storage project in Herefordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 January 2020; the record was last updated on 20 January 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
operationalstatus in REPD
20 January 2020record last updated
Herefordshirecouncil area

Planning timeline

DateStage
23 August 2016Application submitted
1 January 2019Construction started
1 January 2020Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
operational
Record last updated
20 January 2020
Operator or applicant
Anesco (formerly owned by Energy Reservoirs)
Planning authority
Herefordshire, County of
Planning application reference
P162400/F
Address (REPD)
Land West of Clay Hill Pit Larport Farm Larport Lane Dormington
Council area (by location)
Herefordshire
REPD reference
6911

Who decides

ApplicationsHerefordshireUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused6 of 2712%
Onshore wind refused0 of 145%
Battery storage refused0 of 716%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Westhide Solar Farmsolar farm34.6abandoned1.4
Larport, Clay Hill Pit Solar Photovoltaics & Battery storagesolar farm45operational1.4
Frome Valley Solar Farmsolar farm20.6approved, not built5.2
Perserverance Roadbattery storage20approved, not built6.6
Witches Solar Farmsolar farm5operational9.7
Lower Venn Farmsolar farm5operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.054, -2.622).