Energy Projects Near You

Larport, Clay Hill Pit Solar Photovoltaics & Battery storage (45 MW)

Larport, Clay Hill Pit Solar Photovoltaics & Battery storage is a 45 MW solar farm project in Herefordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 July 2024; the record was last updated on 1 July 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

45 MWsolar farm
operationalstatus in REPD
1 July 2024record last updated
Herefordshirecouncil area

Planning timeline

DateStage
25 October 2021Application submitted
27 May 2022Planning permission granted
1 April 2023Construction started
1 July 2024Operational

Project details

Technology
solar farm
Capacity
45 MW
Status (REPD)
operational
Record last updated
1 July 2024
Operator or applicant
Conrad Energy
Planning authority
Herefordshire, County of
Planning application reference
P213963/F
Site area
46.1 ha
Address (REPD)
Larport Solar Farm, W/O Dormington Substation, Larport,
Council area (by location)
Herefordshire
Time to decision
31 weeks
Name in REPD
Larport, Clay Hill Pit - Solar Photovoltaics & Battery storage
REPD reference
9247

The scheme also includes battery storage, recorded separately in REPD (operational).

Who decides

ApplicationsHerefordshireUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused6 of 2712%
Onshore wind refused0 of 145%
Battery storage refused0 of 716%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Westhide Solar Farmsolar farm34.6abandoned<0.1
Land to the west of Clay Hill Pit / Larport Farmbattery storage20operational1.4
Frome Valley Solar Farmsolar farm20.6approved, not built4.6
Perserverance Roadbattery storage20approved, not built5.9
Lower Venn Farmsolar farm5operational8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0657, -2.6285).