Frome Valley Solar Farm (20.6 MW)

Frome Valley Solar Farm is a 20.6 MW solar farm project in Herefordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 July 2025, not yet built; the record was last updated on 27 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20.6 MWsolar farm
approved, not builtstatus in REPD
27 February 2026record last updated
Herefordshirecouncil area

Planning timeline

DateStage
13 June 2024Application submitted
7 July 2025Planning permission granted
7 July 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
20.6 MW
Status (REPD)
approved, not built
Record last updated
27 February 2026
Operator or applicant
Anesco
Planning authority
Herefordshire, County of
Planning application reference
P241510/F
Site area
29.2 ha
Address (REPD)
Yarkhill, Three Crosses, Stoke Edith
Council area (by location)
Herefordshire
Time to decision
56 weeks
Contracts for Difference
AR7a
Name in REPD
Frome Valley - Solar Farm
REPD reference
16355

Who decides

ApplicationsHerefordshireUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused6 of 2712%
Onshore wind refused0 of 145%
Battery storage refused0 of 716%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Larport, Clay Hill Pit Solar Photovoltaics & Battery storagesolar farm45operational4.6
Westhide Solar Farmsolar farm34.6abandoned4.6
Land to the west of Clay Hill Pit / Larport Farmbattery storage20operational5.2
Lower Venn Farmsolar farm5operational8.2
Perserverance Roadbattery storage20approved, not built9.7
Sinton End Farm, Acton Beauchamp Solar Farmsolar farm20refused10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0919, -2.5764).