Westhide Solar Farm (34.6 MW)

Westhide Solar Farm is a 34.6 MW solar farm project in Herefordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 2 February 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

34.6 MWsolar farm
abandonedstatus in REPD
2 February 2022record last updated
Herefordshirecouncil area

Planning timeline

DateStage
20 December 2021Application submitted
17 March 2023Planning permission granted
17 March 2026Permission expired

Project details

Technology
solar farm
Capacity
34.6 MW
Status (REPD)
abandoned
Record last updated
2 February 2022
Operator or applicant
Ersun Westhide SPV Limited
Planning authority
Herefordshire, County of
Planning application reference
P214619/F
Site area
61.7 ha
Address (REPD)
Nw/O Westhide, Hereford
Council area (by location)
Herefordshire
Time to decision
65 weeks
REPD reference
9001

Who decides

ApplicationsHerefordshireUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused6 of 2712%
Onshore wind refused0 of 145%
Battery storage refused0 of 716%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Larport, Clay Hill Pit Solar Photovoltaics & Battery storagesolar farm45operational<0.1
Land to the west of Clay Hill Pit / Larport Farmbattery storage20operational1.4
Frome Valley Solar Farmsolar farm20.6approved, not built4.6
Perserverance Roadbattery storage20approved, not built5.9
Lower Venn Farmsolar farm5operational8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0657, -2.6285).