Reeves Hill (9.2 MW wind farm)

Reeves Hill is a 9.2 MW wind farm project in Herefordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 12 May 2016; the record was last updated on 26 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWwind farm
permission expiredstatus in REPD
26 May 2016record last updated
Herefordshirecouncil area

Planning timeline

DateStage
19 May 2008Application submitted
14 September 2011Planning permission granted
26 November 2015Appeal lodged
26 April 2016Appeal allowed
12 May 2016Permission expired

Project details

Technology
wind farm
Capacity
9.2 MW
Status (REPD)
permission expired
Record last updated
26 May 2016
Operator or applicant
Bolsterstone Innovative Energy
Planning authority
Herefordshire, County of
Planning application reference
NW081479/F
Appeal reference
APP/W1850/W/15/3137440
Turbines
4
Address (REPD)
Reeves Hill, Reeves Lane, near Knighton, Shropshire
Council area (by location)
Herefordshire
Time to decision
173 weeks
REPD reference
4254

Who decides

ApplicationsHerefordshireUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused6 of 2712%
Onshore wind refused0 of 145%
Battery storage refused0 of 716%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3195, -2.9999).