Energy Projects Near You

Solar, wind and battery projects near Knighton (LD7)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LD7 (Powys): 1 approved but not yet running. The largest live scheme is Heartsease Farm (1.2 MW solar farm, approved on 13 March 2023, not yet built), 8.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
1approved, not running
0operational

Projects within 10 km of LD7

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Reeves Hillwind farmwind farm9.2permission expiredupdated May 2016May 2008granted Sep 2011May 2016Herefordshire7.1
Heartsease Farmsolar farmsolar farm1.2approved, not builtupdated Mar 2023Feb 2023granted Mar 2023Mar 2023Powys8.5

Distance from the average position of the LD7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101001.2
Wind farm100000

MW in pipeline: pending, approved and under-construction capacity.

How Powys decides solar, wind and battery applications

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

All projects in Powys

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.