Renewable energy projects in Powys

60 solar, wind or battery projects of 150 kW or more are located in Powys (REPD, July 2026 extract): 9 pending, 20 approved but not running, 12 operational and 9 refused. The council refused 15 of 42 decided applications (36%; UK 19%), with a median 79 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60projects in the council area
9awaiting a decision
20approved, not running
36%of decisions refused

How Powys decides

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

Projects in Powys

Projects of 1 MW and more (42)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Radnor Forest, Llandegley - Nant Mithil Energy Parkwind farmwind farm198application submittedupdated Jan 2026Oct 2025—Jan 2026
Carnedd Wen Wind Farmwind farmwind farm150application withdrawnupdated Sep 2022Dec 2008—Sep 2022
Llandinam Windfarm Repowering and Extensionwind farmwind farm102approved, not built may be out of dateupdated Jun 2020May 2008granted Sep 2015Jun 2020
Mynydd y Gwynt Wind Farmwind farmwind farm89.1refused on appealupdated Jun 2020Jul 2014refused Nov 2015Jun 2020
Garn Fach Wind Farmwind farmwind farm85approved, not builtupdated Nov 2024May 2022granted Oct 2024Nov 2024
Fferm Wynt Llaithddu Cyfwind farmwind farm66.7refusedupdated Sep 2015May 2008refused Sep 2015Sep 2015
Llanbadarn Fynydd Wind Farmwind farmwind farm51refusedupdated Sep 2015Dec 2007refused Sep 2015Sep 2015
Esgair Cwmowenwind farmwind farm51application withdrawnupdated Sep 2014Dec 2003—Sep 2014
Garn Fach Wind Farmbattery storagebattery storage50approved, not builtupdated Nov 2024May 2022granted Oct 2024Nov 2024
Esgair Cwmowenwind farmwind farm47.5application submitted may be out of dateupdated Oct 2018May 2010—Oct 2018
Carno 3wind farmwind farm45approved, not built may be out of dateupdated Dec 2025Jul 2010granted May 2017Dec 2025
Mynydd Waun Fawr Wind Farmwind farmwind farm37.5application withdrawnupdated Sep 2013Oct 2007—Sep 2013
Bryngydfa Wind Farmwind farmwind farm36application submitted may be out of dateupdated Sep 2014Apr 2009—Sep 2014
Garreg Lwydwind farmwind farm34operationalupdated Oct 2017May 2008granted May 2015Oct 2017
Llandinam Windfarmwind farmwind farm31operationalupdated Dec 2009——Dec 2009
Mynydd Yr Hendre Wind Farmwind farmwind farm29.1refusedupdated Mar 2003Feb 1999refused May 2002Mar 2003
Hirddywelwind farmwind farm27application submitted may be out of dateupdated Oct 2017Jun 2010—Oct 2017
Neuadd Goch Bank Wind Farmwind farmwind farm27appeal withdrawnupdated Mar 2020Jan 2012refused Jul 2014Mar 2020
Tirgwyntwind farmwind farm24.6operationalupdated May 2018Sep 2007granted Oct 2010May 2018
Cemmaes 3 Wind Farmwind farmwind farm24appeal withdrawnupdated Nov 2015Feb 2008refused Jan 2013Nov 2015
Nant Carfan Wind Farmwind farmwind farm20.8refusedupdated Dec 2003Apr 1999refused May 2002Dec 2003
Bryn Henllyssolar farmsolar farm20approved, not built may be out of dateupdated Aug 2020Feb 2015granted Jun 2018Aug 2020
Carno 'B' Wind Farmwind farmwind farm16.8operationalupdated Oct 2011Dec 1993granted Aug 1995Oct 2011
Carno 'A' Wind Farmwind farmwind farm16.8operationalupdated Oct 2011Aug 1993granted Aug 1995Oct 2011
Waun Garnowind farmwind farm16.5refusedupdated Mar 2012Apr 2008refused Mar 2012Mar 2012
Bryn Duwind farmwind farm16.4operationalupdated Apr 2005Jul 2000granted Dec 2001Apr 2005
Mynydd Clogau Wind Farm - Extensionwind farmwind farm16application withdrawnupdated Aug 2012Mar 2008—Aug 2012
Carno 'A'and 'B' Wind Farm, (Extension)wind farmwind farm15.6operationalupdated Jan 2010Oct 2003granted Jul 2006Jan 2010
Cemmaes 'C' Wind Farmwind farmwind farm15.3operationalupdated Sep 2010Oct 2000granted Apr 2001Sep 2010
Hirddywell Windfarmwind farmwind farm14.8application withdrawnupdated Jun 2011Aug 2000—Jun 2011
Mynydd Clogau Wind Farmwind farmwind farm14.5operationalupdated May 2009Sep 1998granted May 2002May 2009
Hendy Wind Farmwind farmwind farm14.4under constructionupdated Sep 2020Jul 2014granted Oct 2018Sep 2020
Bryn Blaen Wind Farmwind farmwind farm13.8operationalupdated Feb 2024Dec 2014granted Aug 2016Feb 2024
Bryn titli Windfarmwind farmwind farm9.9operationalupdated Oct 2018Mar 1993granted Aug 1993Oct 2018
Llethercynnon Farm Wind Farmwind farmwind farm7.1refusedupdated Mar 2005Apr 2000refused Jan 2003Mar 2005
Pentre Tumpwind farmwind farm4.5refused on appealupdated Feb 2014Jul 2012refused Dec 2012Feb 2014
Cemmaes 'B' Wind Farmwind farmwind farm3.4operationalupdated Feb 2010Sep 1996granted Mar 1999Feb 2010
The Gaersolar farmsolar farm1.9approved, not builtupdated Mar 2024Aug 2023granted Mar 2024Mar 2024
Tyn y Pantsolar farmsolar farm1.6refusedupdated Nov 2016Dec 2015refused Oct 2016Nov 2016
Heartsease Farmsolar farmsolar farm1.2approved, not builtupdated Mar 2023Feb 2023granted Mar 2023Mar 2023
Coppice Farm, Pen-Rhossolar farmsolar farm1.1approved, not builtupdated Feb 2023Oct 2022granted Jan 2023Feb 2023
Bryn Posteg Landfill Site Solar Array & Battery Storagesolar farmsolar farm1abandonedupdated Nov 2021Jun 2022—Nov 2021
Smaller schemes under 1 MW, mostly rooftop solar (18)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Meadow Springs Country & Leisure Park, Ffinnantsolar farmsolar farm0.9approved, not builtupdated Jan 2026Aug 2025granted Dec 2025Jan 2026
Plas Trannon, Trefeglwyssolar farmsolar farm0.6approved, not builtupdated Mar 2025Jan 2025granted Feb 2025Mar 2025
Cefn y Maes Community Renewable Energy Parkbattery storagebattery storage0.5permission expiredupdated Feb 2020Mar 2017—Feb 2020
Mathrafalsolar farmsolar farm0.5application submittedupdated Sep 2024Aug 2024—Sep 2024
Garthbwt, Clatter Solar Arrayssolar farmsolar farm0.4approved, not builtupdated Apr 2026Sep 2025granted Dec 2025Apr 2026
Glandulas Mawr Farmsolar farmsolar farm0.3approved, not built may be out of dateupdated Jun 2024Mar 2019granted Jun 2019Jun 2024
Royal Welsh Showground, Llanelweddrooftop solarrooftop solar0.3approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023
Rallt Carno Solar Arrayssolar farmsolar farm0.2approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023
Ffrwdgrech Industrial Estaterooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Aug 2023granted Mar 2024Apr 2024
Buttington Old Hall, Buttington Solar PV Arrayssolar farmsolar farm0.2approved, not builtupdated Jan 2022Jan 2022granted Mar 2022Jan 2022
Dyffryn Industrial Estate, Pool Road Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated May 2024Feb 2024granted Apr 2024May 2024
Unit B, Mochdre Industrial Estate - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated May 2024Feb 2024granted May 2024May 2024
The Jointers, Dolforsolar farmsolar farm0.2application submittedMay 2026——
Llysdinam Hall, Charity Trustsolar farmsolar farm0.1approved, not builtupdated Jan 2025Jan 2024granted Oct 2024Jan 2025
Bryn Posteg Landfill Site Solar Array & Battery Storagebattery storagebattery storage—abandonedupdated Jul 2022Jun 2022—Jul 2022
Sychtyn, Llanerfylwind turbinewind turbine—application submittedupdated Dec 2025Oct 2025—Dec 2025
Glynhafren, Old Hallwind turbinewind turbine—application submittedupdated Mar 2026Mar 2026—Mar 2026
Aberffrydlan, Llanwrinwind turbinewind turbine—application submittedJun 2026——

Postcode districts in Powys

DistrictProjects within 10 kmPendingApprovedOperational
LD13120
LD22020
LD32010
LD40000
LD50000
LD61001
LD72010
LD83010
NP86140
SA914133
SY152011
SY164120
SY1715074
SY1812233
SY1911025
SY203111
SY213120
SY221010

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Powys by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.