Carnedd Wen Wind Farm (150 MW)

Carnedd Wen Wind Farm is a 150 MW wind farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 5 February 2020; the record was last updated on 9 September 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

150 MWwind farm
application withdrawnstatus in REPD
9 September 2022record last updated
Powyscouncil area

Planning timeline

DateStage
11 December 2008Application submitted
5 February 2020Application withdrawn

Project details

Technology
wind farm
Capacity
150 MW
Status (REPD)
application withdrawn
Record last updated
9 September 2022
Operator or applicant
Innogy
Planning authority
Powys
Planning application reference
not recorded
Turbines
50
Address (REPD)
Llanbrynmair Forest TAN 8 Strategic Search Area B
Council area (by location)
Powys
REPD reference
3989

Who decides

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

Other large projects within 10 km

ProjectTypeMWStatuskm
Nant Carfan Wind Farmwind farm20.8refused3.0
Cemmaes 'C' Wind Farmwind farm15.3operational7.1
Mynydd Waun Fawr Wind Farmwind farm37.5application withdrawn9.1
Tirgwyntwind farm24.6operational9.3
Mynydd Yr Hendre Wind Farmwind farm29.1refused9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6678, -3.5793).