Energy Projects Near You

Tirgwynt (24.6 MW wind farm)

Tirgwynt is a 24.6 MW wind farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 February 2017; the record was last updated on 1 May 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24.6 MWwind farm
operationalstatus in REPD
1 May 2018record last updated
Powyscouncil area

Planning timeline

DateStage
24 September 2007Application submitted
12 October 2010Planning permission granted
24 December 2015Construction started
15 February 2017Operational

Project details

Technology
wind farm
Capacity
24.6 MW
Status (REPD)
operational
Record last updated
1 May 2018
Operator or applicant
Foresight
Planning authority
Powys
Planning application reference
M/2007/0931
Turbines
12
Address (REPD)
Mynydd yr Hendre & Mynydd Pistyll Du Near Carno, Powys
Council area (by location)
Powys
Time to decision
159 weeks
REPD reference
3707

Who decides

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

Other large projects within 10 km

ProjectTypeMWStatuskm
Mynydd Yr Hendre Wind Farmwind farm29.1refused1.2
Mynydd Waun Fawr Wind Farmwind farm37.5application withdrawn3.0
Esgair Cwmowenwind farm51application withdrawn3.1
Mynydd Clogau Wind Farmwind farm14.5operational4.9
Mynydd Clogau Wind Farm - Extensionwind farm16application withdrawn4.9
Esgair Cwmowenwind farm47.5application submitted6.8
Carno 3wind farm45approved, not built7.7
Carnedd Wen Wind Farmwind farm150application withdrawn9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6105, -3.4791).