Mynydd Clogau Wind Farm - Extension (16 MW)

Mynydd Clogau Wind Farm - Extension is a 16 MW wind farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 18 June 2012; the record was last updated on 22 August 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWwind farm
application withdrawnstatus in REPD
22 August 2012record last updated
Powyscouncil area

Planning timeline

DateStage
10 March 2008Application submitted
18 June 2012Application withdrawn

Project details

Technology
wind farm
Capacity
16 MW
Status (REPD)
application withdrawn
Record last updated
22 August 2012
Operator or applicant
Novera Energy
Planning authority
Powys
Planning application reference
P/2008/0450
Turbines
19
Address (REPD)
Mynydd Clogau, Mynydd Bwrch-y-gors and Mynydd Cerrigllwydion, near Adfa, Newtown, Powys
Council area (by location)
Powys
REPD reference
3706

Who decides

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

Other large projects within 10 km

ProjectTypeMWStatuskm
Mynydd Clogau Wind Farmwind farm14.5operational<0.1
Esgair Cwmowenwind farm51application withdrawn4.5
Mynydd Yr Hendre Wind Farmwind farm29.1refused4.9
Tirgwyntwind farm24.6operational4.9
Esgair Cwmowenwind farm47.5application submitted5.7
Mynydd Waun Fawr Wind Farmwind farm37.5application withdrawn6.5
Carno 3wind farm45approved, not built9.0
Waun Garnowind farm16.5refused9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5784, -3.4285).