Waun Garno (16.5 MW wind farm)

Waun Garno is a 16.5 MW wind farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 6 March 2012; the record was last updated on 7 March 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16.5 MWwind farm
refusedstatus in REPD
7 March 2012record last updated
Powyscouncil area

Planning timeline

DateStage
9 April 2008Application submitted
6 March 2012Refused by the planning authority

Project details

Technology
wind farm
Capacity
16.5 MW
Status (REPD)
refused
Record last updated
7 March 2012
Operator or applicant
Acciona Energy
Planning authority
Powys
Planning application reference
P/2008/0532
Turbines
11
Address (REPD)
Land at Waun Garno Llawr y Glyn, Trefeglwys, Caersws, Powys
Council area (by location)
Powys
Time to decision
204 weeks
REPD reference
3710

Who decides

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

Other large projects within 10 km

ProjectTypeMWStatuskm
Carno 'A' Wind Farmwind farm16.8operational3.0
Carno 'A'and 'B' Wind Farm, (Extension)wind farm15.6operational3.0
Carno 3wind farm45approved, not built3.9
Carno 'B' Wind Farmwind farm16.8operational5.1
Esgair Cwmowenwind farm51application withdrawn7.1
Cemmaes 3 Wind Farmwind farm24appeal withdrawn8.4
Mynydd Yr Hendre Wind Farmwind farm29.1refused9.0
Mynydd Clogau Wind Farmwind farm14.5operational9.5
Mynydd Clogau Wind Farm - Extensionwind farm16application withdrawn9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5278, -3.5425).